Free Interactive Flashcards
Master SQL, Python, Power BI, PMP and more with our free interactive flashcards. Study at your own pace, test your knowledge, and track your progress.
Showing 500 of 500 free flashcards
What is management reserve controlled by?
Show Answer
Senior management or the sponsor, not the PM.
Not at PM's discretion
Ground rules for a team should cover?
Show Answer
Communication norms, meeting etiquette, decision-making process, conflict resolution.
How the team will work together
What is a RACI matrix?
Show Answer
Responsible, Accountable, Consulted, Informed. Clarifies roles for activities.
RACI defines four role types
Risk Management
How should risk communication be incorporated into project status reporting?
Show Answer
Give risks a clearly visible section covering exposure, trends, triggers, response effectiveness, and uncertainty in forecasts. Integrate it with current progress where useful, and use separate focused communication when the audience or decision requires it.
Keep forward-looking exposure visible in reporting
Risk Management
When should risk identification occur?
Show Answer
Risk identification is an iterative process that begins during project initiation and continues throughout the project. It should be performed regularly (e.g., at each review meeting), when significant changes occur, and when the project enters a new phase.
Iterative throughout the project
critical-thinking
What is the purpose of developing project strategy during the planning phase?
Show Answer
To define the overarching approach for achieving project objectives, including how the team will handle risks, engage stakeholders, manage changes, and deliver value
Strategy is the 'how' behind the 'what' of the project objectives
Issue Management
A regulatory announcement introduces new data localization requirements that affect the project's cloud architecture. Is this a risk or an issue?
Show Answer
It is both — the regulatory change is an external event that has ALREADY occurred (the announcement was made), making it an issue. However, it also creates new risks for the future (compliance gaps, redesign needs). The PM should treat it as an issue requiring immediate impact assessment while also updating the risk register.
Already occurred = issue; creates future uncertainty = risk
INR 4,39,000 invested at 12% for 2 years. Future value?
Show Answer
FV = 4,39,000 x (1.12)^2 = INR 5,50,682.
FV = PV x (1+r)^n
critical-thinking
The CFO wants a detailed cost variance report every week, the PMO wants a monthly summary, and the project team wants a simple burn-rate chart. How should the PM handle this?
Show Answer
Create three versions of the financial report from the same data source: weekly detailed for CFO, monthly summary for PMO, and a visual burn-rate dashboard for the team
Different stakeholders need different presentations of the same underlying data
critical-thinking
A team member asks Vikram to make a minor schedule adjustment without going through change control, arguing it is a 'simple re-sequencing.' How should Vikram respond?
Show Answer
Check whether the resequencing changes the approved schedule baseline or exceeds delegated authority. Follow the defined change-control process for a baseline change; a permitted update to the working schedule can be handled under the schedule management plan.
Distinguish working-schedule updates from changes to an approved baseline.
critical-thinking
What are quality control activities in project execution?
Show Answer
Monitoring and recording results of executing quality activities to assess performance and ensure deliverables meet defined quality standards, including inspection, testing, and defect tracking
QC activities verify that the product meets requirements
Sponsor asks to cut quality to meet deadline. What should the PM do?
Show Answer
Explain the effects of the proposed reduction and evaluate safer options. Mandatory safety or compliance requirements cannot be waived; changes to discretionary quality requirements need authorized agreement and updated acceptance criteria.
Assess quality changes against requirements, risk, and approval authority.
critical-thinking
What constitutes 'critical information' in the context of developing an integrated project management plan?
Show Answer
Information that directly impacts project success, including key stakeholder needs, organizational process assets, enterprise environmental factors, constraints, assumptions, and critical success factors
Critical information is anything that shapes planning decisions and cannot be ignored
critical-thinking
During project planning, Meera identifies that her project depends on a government subsidy disbursement that historically arrives 60-90 days late. What should Meera do?
Show Answer
Model the funding delay against planned payments, arrange an authorized cash-flow buffer or bridge funding appropriate to the exposure, and negotiate deferred or phased vendor payment terms where feasible. Escalate the subsidy timing risk to the sponsor.
Plan funding and payment timing together.
PM notices a team member is disengaged. What should they do?
Show Answer
Have a private conversation to understand concerns and re-engage.
Address privately and empathetically
What is the difference between contingency and management reserve?
Show Answer
Contingency = known risks, managed by PM. Management reserve = unknown risks, managed by sponsor.
Different sources of uncertainty
Investment: INR 3,44,000. Returns: INR 6,57,040. ROI?
Show Answer
(6,57,040 - 3,44,000) / 3,44,000 x 100 = 91%.
ROI = (gain - cost) / cost x 100
External failure costs include?
Show Answer
Warranty claims, returns, reputation loss, corrective patches.
Fixing defects after delivery — most expensive
critical-thinking
What is supplier relationship management in project procurement?
Show Answer
Ongoing activities to monitor vendor performance, manage contract changes, resolve issues, maintain communication, and ensure the supplier delivers according to contract terms throughout the procurement lifecycle
Supplier management is continuous from award to closure, not just at the beginning
Issue Management
A government project in Rajasthan faces opposition from a local community about land acquisition. The community is protesting. How should the PM engage?
Show Answer
Stakeholder engagement, not just issue management — understand community concerns, involve local leadership, explore alternative designs that minimize land impact, ensure transparency about project benefits, and work with the government's community liaison team. This requires cultural sensitivity and long-term relationship building.
Community issues = stakeholder engagement, not just PM problem-solving
critical-thinking
What is vendor assessment in procurement management?
Show Answer
The process of evaluating potential sellers against pre-defined criteria (technical capability, cost, past performance, capacity, quality systems) to determine their ability to deliver the required procurement
Vendor assessment is a structured evaluation, not just price comparison
critical-thinking
Rahul is developing the project management plan for a smart city IoT deployment. The scope management plan says requirements will be gathered via workshops, but the communications management plan says stakeholders are distributed across 3 time zones with limited overlap. What should Rahul address?
Show Answer
The integration issue between the scope and communications plans — develop a virtual workshop strategy and document how requirements gathering will work across time zones
When subsidiary plans conflict, the PM must resolve the integration gaps
critical-thinking
A software development activity requires 80 hours of effort. If 2 developers are assigned at 6 productive hours per day each, what is the estimated duration in working days?
Show Answer
80 hours / (2 developers x 6 hours/day) = 6.67 days, which rounds up to 7 working days
Duration = Effort / (Team Size x Productive Hours per Day)
critical-thinking
What is the difference between contingency reserves and management reserves in financial management?
Show Answer
Contingency reserves address known-unknown risks (identified risks with probability/impact assessments) and are controlled by the project manager with defined approval thresholds. Management reserves address unknown-unknown risks and are controlled by senior management, not the PM
Known risks use contingency (PM-controlled); unknown risks use management reserve (senior management-controlled)
Risk Management
Two risks have the same probability-impact score: (A) regulatory fine of ₹2 crores and (B) schedule delay of 2 weeks. When resources are limited, which should be prioritized?
Show Answer
Use the defined criteria and expert judgment to compare urgency, regulatory obligations, dependencies, overall consequences, and feasible response windows. The equal score alone does not determine priority; either risk could require earlier action depending on the facts.
Equal scores require contextual prioritization
critical-thinking
A vendor has been consistently delivering quality work ahead of schedule. The PM wants to strengthen the relationship for future projects. What should the PM do?
Show Answer
Provide formal positive feedback through the vendor's performance evaluation, discuss a long-term partnership framework, and ensure they are considered for future procurement opportunities
Good vendor relationships are strategic assets — invest in them through formal channels
Technical feasibility means?
Show Answer
The organization has or can acquire the technology and skills needed.
Can we build it?
critical-thinking
During sprint retrospectives, the team consistently identifies 'poor requirement clarity' as the top impediment. What continuous improvement action should the PM facilitate?
Show Answer
Implement a requirement refinement checklist, introduce a 'definition of ready' for user stories, and track whether the issue reduces in the next sprint
Retrospective findings must lead to specific, actionable process changes that are tracked for effectiveness
Risk Management
A mining project in Odisha faces community opposition due to environmental concerns. The PM identifies this as a sustainability risk. What risk response strategies are most appropriate?
Show Answer
Mitigate the threat through appropriate environmental assessments, design controls, and meaningful community engagement. Consider avoidance through a compliant alternative site or scope, and transfer only insurable financial exposure where suitable coverage exists. Partnership with an NGO may support mitigation; it does not make share a threat-response strategy.
Threat responses include mitigate, avoid, transfer, accept, or escalate
critical-thinking
During dependency coordination, the PM discovers that two activities from different teams have the same finish milestone but no formal dependency link. Activity X finishes day 30 and Activity Y finishes day 28. What risk does this create?
Show Answer
A hidden schedule risk: if Activity Y slips, it may not be obvious it affects the overall milestone since the dependency is undocumented
Undocumented dependencies create invisible schedule risks
Backlog = 115 points, velocity = 37 points/sprint. How many sprints?
Show Answer
115 / 37 = 3.1. Round up to 4 sprints.
Sprints = ceiling(backlog / velocity)
Virtual team management challenges?
Show Answer
Communication gaps, time zone differences, reduced trust, limited spontaneous collaboration.
Distance creates new management challenges
Path A(5d)->B(7d)->C(10d) = 22 days. Path A(5d)->D(5d) = 10 days. Total float on second path?
Show Answer
12 days of total float.
Total float = critical path - alternative path
critical-thinking
Rajesh's project has a cost baseline of INR 3 crore. He has INR 20 lakh in contingency reserve (for known risks) and INR 30 lakh in management reserve (for unknown risks). A known risk materializes costing INR 25 lakh. How should Rajesh fund this?
Show Answer
Use the INR 20 lakh contingency according to its authority rules, quantify the INR 5 lakh shortfall, and seek an approved budget or funding adjustment through the defined governance process. Management reserve use must comply with its permitted purpose and approval rules.
An exhausted contingency reserve requires authorized funding decisions; it does not automatically authorize management reserve.
Compliance
What does a compliance KPI measure?
Show Answer
It measures performance against applicable legal, contractual, or organizational requirements, such as the percentage of requests handled within the mandated deadline or controls with verified evidence. Compliance indicators can form part of the project's overall performance dashboard.
Measure adherence to the applicable requirement
Upward communication is?
Show Answer
Communication from team to sponsor/management. Needs clarity and evidence.
To the chain above
Issue Management
A supplier delivers components that fail quality testing. The PM estimates 3 weeks to source alternatives. What is the immediate impact evaluation priority?
Show Answer
Assess any safety or compliance implications and contain affected components where necessary. Then evaluate schedule dependencies, cost, quality, scope, and operational impacts together and select an authorized response based on consequence and urgency.
Assess the full impact and any immediate containment need
Governance
What are governance rules in project management?
Show Answer
Formally documented policies, standards, and procedures that define how decisions are made, how authority is exercised, how conflicts are resolved, and how the project is monitored and controlled.
Rules = the 'how' of governance
Governance
A project for a public hospital in Delhi must comply with India's Digital Personal Data Protection Act. The PM wants to know what governance policies apply. Where should they look first?
Show Answer
The organization's data governance policy and compliance register — these should map applicable laws to specific project controls and requirements. The PM should also consult the legal team for jurisdiction-specific guidance.
Start with organizational compliance registers
Change Management
What is the PM's responsibility during change implementation?
Show Answer
The PM coordinates implementation, ensures the change is executed per the approved scope, monitors for unintended consequences, manages any new risks introduced by the change, and reports progress to the CCB and stakeholders.
PM coordinates, monitors, and reports during implementation
critical-thinking
Vikram's project management plan baseline was approved 3 months ago. The customer has just submitted a formal change request that has been approved by the Change Control Board. What must Vikram do with the plan?
Show Answer
Update the affected subsidiary plans and the overall project management plan to reflect the approved change, then communicate the updated baselines to all stakeholders
Approved changes must be reflected in the plan — the baseline is updated only through formal change control
Governance
A PM notices the steering committee only reads the executive summary of the 15-page governance report. What should the PM do?
Show Answer
Restructure the report to front-load critical information with a one-page dashboard (RAG status, key metrics, decisions needed), and move detailed analysis to appendices — governance reporting must be consumable by busy executives.
Adapt reporting to audience needs
What is a milestone chart?
Show Answer
A chart showing major milestones over time without activity bars.
High-level view
critical-thinking
Priya is defining resource requirements for a data center construction project. She needs structural engineers for months 2-4, electrical engineers for months 3-7, and HVAC specialists for months 5-8. What technique should Priya use to document these requirements?
Show Answer
A resource breakdown structure (RBS) combined with a responsibility assignment matrix (RAM/RACI) that maps resource types to project phases and activities
RBS + RAM together provide both the 'what' and 'who' of resource planning
INR 4,25,000 invested at 12% for 3 years. Future value?
Show Answer
FV = 4,25,000 x (1.12)^3 = INR 5,97,094.
FV = PV x (1+r)^n
Risk Management
When is quantitative risk analysis most appropriate?
Show Answer
When the project has significant risk exposure, when high-value decisions require numerical precision (e.g., contingency reserve calculation), when qualitative analysis is insufficient to support decision-making, or when the organization requires probabilistic schedule/cost estimates.
When numbers are needed for decisions
What is a scatter diagram?
Show Answer
A graph showing the relationship between two variables.
Identifies correlation
Change Management
A project has approved 17 changes in 6 months, each averaging 3 days to process through the CCB. The CCB meets biweekly. The team complains about the backlog. What should the PM do?
Show Answer
Analyze whether the change volume indicates a design or requirements problem, consider tiering changes by impact (fast-track low-impact changes), and discuss CCB meeting frequency with the board. High change volume may signal underlying project issues.
High change volume = deeper problem
INR 3,62,000 invested at 10% for 8 years. Future value?
Show Answer
FV = 3,62,000 x (1.10)^8 = INR 7,75,979.
FV = PV x (1+r)^n
What is a buffer in critical chain?
Show Answer
Time reserved to protect the project schedule against uncertainty.
Protection against delays
Critical dependency from another team is delayed. What should the PM do?
Show Answer
Confirm the delay with the dependency owner, assess its effect on the schedule, and identify recovery options. Coordinate the response and escalate under the agreed thresholds; update forecasts and seek approval for any required baseline changes.
Coordinate dependencies and quantify impact before selecting the response.
How are stakeholder engagement and stakeholder management related?
Show Answer
Stakeholder engagement is the active involvement and relationship work within stakeholder management. Stakeholder management also includes identifying and analyzing stakeholders, planning engagement, and monitoring and adapting how expectations are addressed.
Engagement is part of stakeholder management
Sponsor wants to reduce testing time. What should the PM do?
Show Answer
Assess whether the proposed testing change still verifies the required quality and compliance criteria. Present residual risk and alternative methods, and obtain any needed approval; do not omit mandatory verification merely to meet a date.
Testing duration can change if required evidence and acceptable risk are maintained.
Kepner-Tregoe decision making uses?
Show Answer
Situation analysis, problem analysis, decision analysis, potential problem analysis.
Structured decision process
Risk Management
What is expected monetary value (EMV) analysis and how is it calculated?
Show Answer
EMV = Probability of risk occurring × Financial impact if it occurs. It quantifies risk exposure in monetary terms. For opportunities, EMV is positive (potential gain); for threats, it is negative (potential loss). EMV helps prioritize risks and calculate contingency reserves.
EMV = Probability × Impact ($)
PM discovers a serious risk that was missed. What should they do?
Show Answer
Immediately assess, develop response, inform stakeholders, update risk register.
No blame -- just act
Team identifies a better way to do work. What should the PM do?
Show Answer
Evaluate the proposed improvement with the team, test it where appropriate, and update the process if evidence supports it. Obtain approval only where the change affects mandated controls or exceeds the team's authority.
Empower improvement within the team's authority.
Can the Sprint Goal be changed during the Sprint?
Show Answer
No. The Sprint Goal provides consistency.
Sprint Goal is fixed
critical-thinking
The organization has a policy of using only Indian vendors for government-funded projects. The best technical solution comes from a German company. What should the PM do?
Show Answer
Document the vendor comparison showing the German vendor's superior solution, explore whether the policy allows for sole-source exceptions with justification, or identify an Indian partner for the German vendor
Organizational policies can sometimes be navigated through formal exception processes or partnerships
Risk Management
A project team for a wind energy installation in Gujarat identifies risks only at the beginning and does not revisit them. After 4 months, a monsoon delay was not on their risk register. What process failure occurred?
Show Answer
Risk identification was not iterative — it was treated as a one-time activity rather than a continuous process. New risks emerge throughout the project, especially from environmental and external changes.
Risk identification must be continuous
critical-thinking
What is the difference between a dependency and a constraint in scheduling?
Show Answer
A dependency is a logical relationship between activities (one depends on another), while a constraint is an external limitation on when an activity can start or finish (e.g., fixed dates, resource availability, regulatory deadlines)
Dependencies express activity logic; constraints limit permissible dates or resource use and may have internal or external origins.
What is resource smoothing?
Show Answer
Adjusting activities within available float to smooth resource demand without changing the critical path or project completion date.
Smoothing preserves completion and respects available float.
What is value engineering?
Show Answer
Analyzing functions to achieve necessary functions at the lowest cost.
Cost optimization without loss of function
INR 2,97,000 invested at 5% for 8 years. Future value?
Show Answer
FV = 2,97,000 x (1.05)^8 = INR 4,38,804.
FV = PV x (1+r)^n
critical-thinking
Priya plans to track project costs monthly. Her sponsor insists on weekly cost reporting for the first 3 months because the project is in a high-visibility phase. What should Priya do?
Show Answer
Align with the sponsor's requirement for weekly reporting during the high-visibility phase, then revert to monthly reporting once the phase transitions, documenting this in the cost management plan
The cost management plan should reflect the actual reporting needs and can be adjusted with stakeholder agreement
Risk Management
A PM uses assumption analysis for risk identification. What are they looking for?
Show Answer
Examine inaccurate, unstable, or inconsistent assumptions and constraints that could affect project objectives. Validate their basis and document actionable risks where uncertainty could create a positive or negative effect.
Challenge assumptions that could affect objectives
What is Tuckman's model of team development?
Show Answer
Forming, Storming, Norming, Performing, Adjourning.
Five stages of team development
critical-thinking
What is the key difference between a needs assessment and a business case in the context of project initiation?
Show Answer
A needs assessment identifies what stakeholders require and current gaps, while a business case justifies the investment by quantifying benefits against costs
One identifies the gap, the other justifies closing it
critical-thinking
At month 6 of a 12-month project, CPI has been consistently 0.85. The PM forecasts the project will complete at 118% of the original budget. What should the PM do?
Show Answer
Present a formal forecast to the sponsor with the EAC, propose corrective actions (value engineering, scope re-prioritization, or additional funding request), and update the risk register
A CPI of 0.85 sustained means significant overrun is likely — early escalation is critical
Team is burnt out from long sprints. What should the PM do?
Show Answer
Reduce WIP, improve work-life balance, discuss sustainable pace.
Sustainable pace is essential
INR 2,11,000 needed in 7 years at 8% discount. Present value?
Show Answer
PV = 2,11,000 / (1.08)^7 = INR 1,23,116.
PV = FV / (1+r)^n
How many potential communication channels exist among n participants if every pair can communicate directly?
Show Answer
n(n-1)/2 potential pairwise channels. This assumes one channel per unordered pair; the project's actual communication network may use fewer channels.
Count unique pairs
Path A(14d)->B(4d)->C(8d) = 26 days. Path A(14d)->D(18d) = 32 days. Total float on second path?
Show Answer
0 days of total float on the second path. It is the critical path at 32 days; the 26-day first path has 6 days of path float under the stated simple network.
Identify the longest path first; negative float requires an unmet date constraint.
INR 1,22,000 invested at 8% for 2 years. Future value?
Show Answer
FV = 1,22,000 x (1.08)^2 = INR 1,42,301.
FV = PV x (1+r)^n
Investment: INR 2,50,000. Returns: INR 3,60,000. ROI?
Show Answer
(3,60,000 - 2,50,000) / 2,50,000 x 100 = 44%.
ROI = (gain - cost) / cost x 100
Situational leadership model?
Show Answer
Directing, Coaching, Supporting, Delegating based on follower competence and commitment.
Match style to follower readiness
Critical chain method is?
Show Answer
A schedule method that accounts for resource constraints and uses buffers.
Goldratt's theory of constraints
PV = INR 83,000, EV = INR 69,000. SPI?
Show Answer
SPI = 69,000 / 83,000 = 0.83. Behind schedule.
SPI = EV / PV. < 1 means behind.
INR 4,77,000 needed in 2 years at 10% discount. Present value?
Show Answer
PV = 4,77,000 / (1.10)^2 = INR 3,94,215.
PV = FV / (1+r)^n
PV = INR 68,000, EV = INR 36,000. SPI?
Show Answer
SPI = 36,000 / 68,000 = 0.53. Behind schedule.
SPI = EV / PV. < 1 means behind.
Issue Management
What does 'working with stakeholders to resolve issues' involve?
Show Answer
Identifying affected stakeholders, communicating the issue and its impact, negotiating solutions that balance competing interests, obtaining necessary approvals, managing expectations, and ensuring stakeholder concerns are addressed in the resolution.
Identify → Communicate → Negotiate → Approve → Manage expectations
Servant leader prioritizes?
Show Answer
The team's needs over their own. Team growth, well-being, and autonomy.
Team over leader
Compliance
How should a PM assess consequence severity when the organization has no prior incident data?
Show Answer
Use industry benchmarks, regulatory penalty schedules, expert judgment from legal/compliance teams, and scenario analysis to estimate severity. Also consider worst-case scenarios and their probability-weighted impact.
Benchmarks and expert judgment fill data gaps
Issue Management
What does 'continuously confirm blockers' mean?
Show Answer
Regularly verify whether reported blockers are still active, assess whether resolution progress is being made, and confirm that resolved blockers are properly closed. This prevents stale issues from cluttering the issue log and ensures active blockers get attention.
Verify blocker status regularly
critical-thinking
What is the difference between project scope and product scope?
Show Answer
Project scope is the work required to deliver a product, service, or result with specified features and functions. Product scope is the features and functions that characterize that product, service, or result.
Project scope describes the work; product scope describes the result's characteristics.
Issue Management
A software bug affects a client's production system. The client demands immediate fix. The dev team says it requires 5 days minimum. What stakeholder resolution approach should the PM use?
Show Answer
Facilitate a structured discussion: quantify the client's actual business impact, explore interim workarounds, negotiate a phased fix (hotfix for critical function + full fix in 5 days), and document the agreement. The PM must balance urgency with technical reality.
Negotiate: quantify impact → explore workarounds → phased fix
What is a business case?
Show Answer
A document explaining the need for the project and its expected benefits, costs, and success criteria.
Justification for the project
Feedback should be?
Show Answer
Timely, specific, fact-based, and actionable.
Characteristics of good feedback
Governance
What is governance reporting in project management?
Show Answer
The structured communication of project performance, risks, issues, and compliance status to governance bodies (steering committee, project board, sponsor) to enable informed oversight and timely decision-making.
Reporting = communication to governance bodies
Compliance
A compliance requirement is classified as 'critical' but the organization's current capability to meet it is assessed as 'low.' What does this combination indicate?
Show Answer
Treat this as a significant compliance gap. Work with specialists to build capability, select a compliant design or delivery option, and replan or escalate the required resources and timing. Any waiver, exception, or revised obligation must be legally and contractually permissible and authorized.
Close the capability gap through an authorized compliant approach
Issue Management
A PM is so focused on executing risk responses that they fail to notice a risk has already materialized into an issue. What governance mechanism would catch this?
Show Answer
Regular risk review meetings that compare current project state against risk triggers, issue log audits that cross-reference with the risk register, and escalation triggers that require reporting when risk events occur.
Risk reviews catch the transition
critical-thinking
During quality requirements collection, a stakeholder requests a feature that exceeds industry standards for similar products. The team estimates it would add 20% to cost and 3 months to schedule. What should the PM do?
Show Answer
Document the requested quality requirement, analyze its value and impacts, and agree the requirement with the authorized stakeholders. If it changes an approved baseline, follow the applicable change-control process.
Use requirements agreement during planning; baseline changes follow the defined control process.
critical-thinking
What does 'ensuring measurable benefits' mean in value-based delivery?
Show Answer
Defining specific, quantifiable benefit metrics before delivery begins, establishing a benefits realization plan, and creating mechanisms to measure and verify that benefits are actually achieved after project completion
Benefits must be measurable both during and after the project
What is PESTLE analysis?
Show Answer
Political, Economic, Social, Technological, Legal, Environmental factors.
Macro-environmental analysis
Backlog = 97 points, velocity = 45 points/sprint. How many sprints?
Show Answer
97 / 45 = 2.2. Round up to 3 sprints.
Sprints = ceiling(backlog / velocity)
In ADKAR, what is Reinforcement?
Show Answer
Sustaining the change over time.
Keep the change
Belbin team roles include?
Show Answer
Plant, Coordinator, Resource Investigator, Monitor Evaluator, Implementer, Completer Finisher, Teamworker, Shaper, and Specialist.
Nine team role types
critical-thinking
What does confirming procurement objectives mean?
Show Answer
Verifying that the selected procurement approach and vendor will deliver the required outcomes by aligning contract deliverables with project objectives and ensuring measurable acceptance criteria
Procurement objectives must be traceable to project objectives
critical-thinking
A project requires a specialized CNC machine for 3 weeks. The organization owns one, but it is currently allocated to another project finishing 2 weeks after this project needs it. What should the PM do?
Show Answer
Negotiate with the other project's PM for a temporary handover, explore rental options, or adjust the schedule to accommodate the machine's availability
Resource conflicts between projects require negotiation at the PMO or functional manager level
Organization rewards heroism over sustainable pace. What should the PM do?
Show Answer
Demonstrate sustainable pace delivers better results. Lead by example.
Show, do not tell
Risk Management
A PM reports to the steering committee that 'no major risks were identified this month.' The risk register actually has 5 high-priority risks that were identified last month but have not been updated. What communication failure occurred?
Show Answer
Misleading risk communication — the PM presented an incomplete picture by not reporting on existing high-priority risks. Risk status should include both new risks and the current status of previously identified risks.
Communication must cover all risk status, not just new risks
critical-thinking
During financial planning, the finance department asks Deepa to justify every line item in her INR 45 lakh project budget. Deepa's estimates are based on expert judgment and historical data. What should Deepa provide?
Show Answer
A cost breakdown structure (CBS) showing how each budget line maps to WBS work packages, with supporting evidence from historical data and expert input rationale
A CBS provides the traceability that finance departments require for budget approval
Organization has fail-fast culture but PM is risk-averse. What should they do?
Show Answer
Understand the context for risk appetite and adjust approach.
Culture shapes behavior
Motivation theories: Maslow?
Show Answer
Hierarchy: Physiological, Safety, Social, Esteem, Self-actualization.
Five levels of needs
How to gain stakeholder buy-in?
Show Answer
Early involvement, transparent communication, demonstrate value, address concerns.
Engagement, not persuasion
critical-thinking
The PM reviews her 18-month project at month 9. SV = 0 and SPI = 1.0, but CPI = 0.75. What does this tell her about the project health?
Show Answer
EV equals PV at the status date, so cumulative budgeted work matches the plan. CPI = 0.75 shows unfavorable cost efficiency: the project earns only 0.75 units of budgeted work per unit spent. Investigate cost variance and check the critical path and milestone forecasts before concluding the project is on schedule.
EVM progress must be interpreted with the actual schedule and critical path.
Compliance
What is the difference between a compliance corrective action and a project corrective action?
Show Answer
A compliance corrective action specifically addresses a failure to meet a regulatory, legal, or policy requirement, and often requires evidence of remediation for auditors. A project corrective action addresses any deviation from the project plan. Compliance actions may have legal deadlines.
Compliance CA = legal dimension; Project CA = plan dimension
Investment: INR 3,11,000. Annual benefit: INR 42,000 for 4 years at 10%. NPV?
Show Answer
Total PV of benefits: INR 1,33,134. NPV = 1,33,134 - 3,11,000 = INR -1,77,866. Project is not viable at this rate.
NPV = PV of benefits - PV of costs
Compliance
When should a project conduct a compliance audit?
Show Answer
Set compliance audits and verification at the intervals and trigger points required by applicable rules, contracts, and the compliance plan. These may include key milestones, stage gates, material changes, incidents, and closure. Confirm any statutory audit frequency with qualified specialists.
Use the actual obligation and compliance plan for audit timing
Governance
What are success measures in project governance?
Show Answer
Quantifiable and qualitative criteria that define what project success looks like, including delivery metrics (time, cost, scope), outcome metrics (benefits realization, stakeholder satisfaction), and governance metrics (compliance rate, issue resolution time).
Success measures = how you know the project succeeded
Governance
A governance report shows CPI at 0.82 and SPI at 0.75 for a ₹8 crore highway construction project in Tamil Nadu. The project is 6 months into a 24-month timeline. What should the report emphasize?
Show Answer
Early warning indicators showing both cost and schedule deterioration, root cause analysis of the variance, mitigation actions already taken, and specific decisions needed from the steering committee to address the trajectory.
Governance reports highlight problems AND needed decisions
PM discovers a team member has a conflict of interest. What should they do?
Show Answer
Have the affected team member disclose the conflict to the designated authority, document and assess it, and apply the required recusal or mitigation under organizational policy.
Use the policy's disclosure and conflict-management process.
Baseline is?
Show Answer
An approved version of a project plan against which performance is measured.
Approved plan for comparison
critical-thinking
What is procurement strategy and what does it encompass?
Show Answer
The overall approach to acquiring goods and services, including make-vs-buy decisions, sourcing strategies (single vs. multiple suppliers), contract type selection, risk allocation, and vendor relationship models
Strategy answers: what to buy, from how many sources, under what terms, and how to manage the relationship
Investment: INR 3,25,000. Returns: INR 5,94,750. ROI?
Show Answer
(5,94,750 - 3,25,000) / 3,25,000 x 100 = 83%.
ROI = (gain - cost) / cost x 100
What is a stakeholder engagement assessment matrix?
Show Answer
A tool comparing current vs desired stakeholder engagement levels.
Gap analysis for stakeholders
Risk owner is unavailable. What should the PM do?
Show Answer
Assign a backup owner. Do not let risks sit unmonitored.
Every risk needs an owner
critical-thinking
What is activity duration estimating versus effort estimating in schedule management?
Show Answer
Duration estimating predicts the total elapsed time (in calendar units) to complete an activity, accounting for resources and constraints; effort estimating predicts the total person-hours of work required, without accounting for calendar constraints
Duration = elapsed time; Effort = work input. They are related but different measures
Organization mandates waterfall but PM wants Agile. What should they do?
Show Answer
Assess the reasons for the mandate and the project's uncertainty, then propose an authorized exception or permitted hybrid approach with supporting evidence. Use the mandated approach unless the organization's governance approves tailoring.
Approach selection must respect organizational constraints and approved tailoring.
Governance
What governance procedure would best prevent a situation where a project continues spending after it has clearly missed its business case?
Show Answer
A stage-gate review procedure where each project phase requires formal reassessment of the business case before the next tranche of funding is released.
Stage gates = business case checkpoints
Change request from a junior team member to modify a process. What should the PM do?
Show Answer
Evaluate the suggestion on its merits. Good ideas come from anywhere.
Evaluate on merit
critical-thinking
A project has a planned duration of 16 months. At actual elapsed time of 6 months, its earned schedule is 5.1 months. Assuming its time-based performance continues, what are SPI(t), forecast total duration, and remaining duration?
Show Answer
SPI(t) = earned schedule / actual time = 5.1/6 = 0.85. Forecast total duration = 16/0.85 = 18.82 months. Forecast remaining duration = 18.82 - 6 = 12.82 months. This is an earned-schedule forecast under the stated assumption.
Time-based forecasts use earned schedule and actual time; cost-based EV and BAC are not months.
Team member falsified progress reports. What should the PM do?
Show Answer
Address immediately, document, escalate per organizational policy.
Integrity violations are serious
Risk Management
How does a PM determine if a risk response is effective?
Show Answer
By measuring whether the risk's probability or impact has decreased to an acceptable level, whether residual risk is within tolerance, and whether the response cost was justified by the risk reduction achieved. Metrics from the risk register and periodic risk audits provide evidence.
Probability/impact reduction + cost-benefit validation
Issue Management
A PM's risk register shows: 'Risk: Vendor delay, Trigger: Vendor misses first milestone, Contingency: Activate backup vendor.' The vendor misses the milestone. What happens now?
Show Answer
The trigger has fired and the contingency plan must be activated immediately — the PM should contact the backup vendor while the risk owner monitors the original vendor's recovery plan. If the vendor delay causes actual project impact, the risk formally becomes an issue.
Trigger fires = activate contingency
Path A(20d)->B(16d)->C(8d) = 44 days. Path A(20d)->D(7d) = 27 days. Total float on second path?
Show Answer
17 days of total float.
Total float = critical path - alternative path
PM realizes the project charter is outdated. What should they do?
Show Answer
Verify which charter information is outdated and review it with the sponsor or designated authority. Obtain the required approval for any change and communicate the authorized version.
The charter records authorization; changes require the proper authority.
Equipment costs INR 5,86,000. Straight-line over 8 years, salvage INR 99,620. Annual depreciation?
Show Answer
(5,86,000 - 99,620) / 8 = INR 60,798 per year.
Depreciation = (cost - salvage) / useful life
Investment: INR 2,58,000. Returns: INR 3,19,920. ROI?
Show Answer
(3,19,920 - 2,58,000) / 2,58,000 x 100 = 24%.
ROI = (gain - cost) / cost x 100
critical-thinking
A project backlog has 35 user stories. Using value-based prioritization, the PM ranks them by: (a) revenue impact, (b) user adoption impact, (c) regulatory compliance, (d) technical debt reduction. What is the correct priority order?
Show Answer
Identify mandatory compliance deadlines and dependencies, then agree prioritization using expected value, urgency, risk, effort, and stakeholder feedback. The information given does not determine a unique order among revenue, adoption, and technical debt work.
Prioritization is contextual; technical debt can enable or protect high-value delivery.
PDCA cycle stands for?
Show Answer
PDCA stands for Plan-Do-Check-Act. PDSA is a related variant meaning Plan-Do-Study-Act.
Check belongs to PDCA; Study belongs to PDSA.
Under the conventional Six Sigma assumption of a 1.5-sigma long-term mean shift, what defect rate is commonly quoted?
Show Answer
Approximately 3.4 defects per million opportunities.
The 3.4 DPMO convention assumes a 1.5-sigma shift.
Risk Management
A PM is managing a project that involves building a payment gateway. What security risks should be specifically identified?
Show Answer
Identify data breaches, unauthorized access, denial-of-service attacks, payment fraud, key-management failures, integration vulnerabilities, insider threats, and failure to meet applicable payment security requirements such as PCI DSS. Confirm contractual and legal obligations with the relevant specialists.
Payment gateway = high security risk surface
Power/Interest grid classifies stakeholders by?
Show Answer
Power (authority/influence) and Interest (concern/involvement).
Four-quadrant classification
critical-thinking
What is the fundamental difference between quality assurance (QA) and quality control (QC) in project management?
Show Answer
Quality Assurance is process-oriented: it audits and improves the processes that create deliverables. Quality Control is product-oriented: it inspects and tests deliverables to find defects. QA prevents defects; QC detects defects
QA improves processes; QC verifies deliverables. They can operate throughout delivery.
Investment: INR 1,32,000. Annual benefit: INR 76,000 for 5 years at 12%. NPV?
Show Answer
Total PV of benefits: INR 2,73,963. NPV = 2,73,963 - 1,32,000 = INR 1,41,963. Project is financially viable.
NPV = PV of benefits - PV of costs
critical-thinking
What is procurement execution in project management?
Show Answer
The process of obtaining seller responses, selecting vendors, awarding contracts, and administering the procurement relationship until contract closure
Execution turns the procurement plan into actual agreements with vendors
critical-thinking
Karthik estimated a data migration activity at 40 person-hours. When the work started, two team members reported they needed 30 hours each because the legacy database had undocumented dependencies. What estimation technique failure likely occurred?
Show Answer
The estimate did not adequately validate assumptions about legacy dependencies and complexity. Document the newly discovered work, reassess the estimate with the team, and improve assumption validation; the scenario does not reveal whether analogous or another technique was used.
A poor estimate can arise from missing information under any estimation technique.
critical-thinking
A project is trending over budget but the PM believes the overrun is temporary due to a one-time equipment purchase. CPI is 0.88 at month 3. The PM wants to continue without reporting to the sponsor. What is wrong with this approach?
Show Answer
The PM cannot unilaterally decide that an overrun is temporary — variance thresholds defined in the cost management plan trigger escalation. Hiding variances erodes stakeholder trust and may violate governance
Thresholds exist for a reason — exceeding them requires escalation regardless of the PM's opinion
Investment: INR 3,77,000. Annual benefit: INR 76,000. Simple payback period?
Show Answer
3,77,000 / 76,000 = 5.0 years.
Simple payback = investment / annual benefit
Risk Management
When should a risk owner escalate a risk response to the PM?
Show Answer
When the risk trigger occurs, when the risk's probability or impact changes significantly, when the response strategy is no longer effective, when additional resources are needed, or when the risk becomes an issue requiring governance intervention.
Trigger, change, ineffectiveness, resource need, or escalation
Equipment costs INR 1,98,000. Straight-line over 8 years, salvage INR 39,600. Annual depreciation?
Show Answer
(1,98,000 - 39,600) / 8 = INR 19,800 per year.
Depreciation = (cost - salvage) / useful life
Issue Management
What is a blocker confirmation process and how does it work?
Show Answer
Review active blockers at intervals and trigger points suited to their urgency and the team's working practices. Confirm impact and ownership, check progress, escalate at agreed thresholds, and verify resolution before closure.
Tailor review frequency and confirm actual resolution
Compliance
What is a compliance register and why is it essential?
Show Answer
A compliance register is a structured document that identifies all applicable compliance requirements, maps them to project activities, assigns ownership, defines evidence needed, and tracks compliance status. It is essential because it makes compliance visible, manageable, and auditable.
The compliance register = the project's compliance map
Path A(19d)->B(13d)->C(11d) = 43 days. Path A(19d)->D(5d) = 24 days. Total float on second path?
Show Answer
19 days of total float.
Total float = critical path - alternative path
Compliance
How does classifying compliance requirements help with project planning?
Show Answer
Classification helps establish ownership, evidence, review frequency, resource allocation, and response urgency. Identify each requirement's authority and applicability first; prioritize implementation without treating a mandatory duty as optional because its assessed consequence is lower.
Classification guides management while preserving obligations
critical-thinking
What is value-based prioritization and how does it differ from traditional priority setting?
Show Answer
Value-based prioritization ranks project work by its contribution to business value, benefits realization, and stakeholder outcomes, rather than by technical dependency, urgency, or ease of implementation alone
Traditional priority often uses urgency; value-based uses impact on objectives
critical-thinking
A project to automate invoice processing can be done via: (a) custom RPA development (INR 35 lakh, 6 months, 95% automation), (b) off-the-shelf software (INR 50 lakh, 3 months, 80% automation), or (c) outsourced BPO (INR 28 lakh ongoing, 90% automation, 1 month setup). What should the PM evaluate?
Show Answer
Total cost of ownership over 3 years, automation percentage, implementation speed, data security, vendor dependency, and organizational capability to maintain each solution
Alternative analysis must compare all viable options across multiple value dimensions
INR 3,52,000 needed in 8 years at 5% discount. Present value?
Show Answer
PV = 3,52,000 / (1.05)^8 = INR 2,38,247.
PV = FV / (1+r)^n
Risk Management
What are five common response strategies for opportunities?
Show Answer
Exploit to make the opportunity occur; enhance its probability or benefit; share ownership with a party better able to capture it; accept it without pursuing additional action, with preparation where appropriate; or escalate it to an owner outside the project when it exceeds project scope or authority.
Exploit, enhance, share, accept, escalate
Risk Management
What is security risk management in projects?
Show Answer
The process of identifying, assessing, and responding to risks that could compromise the confidentiality, integrity, or availability of project information, systems, or physical assets. It integrates cybersecurity, physical security, and information security into the project risk framework.
Security risk = CIA triad protection
critical-thinking
Meera's organization requires all projects above INR 1 crore to use Earned Value Management. Her project is INR 2.5 crore. However, her team has no EVM experience. What should Meera do?
Show Answer
Implement EVM with proper training for the team, define the measurement points (control accounts) in the cost management plan, and establish reporting cadence with the sponsor
Organizational requirements must be met — EVM training and control account setup are the PM's responsibility
Governance
Meera is the PM for a hospital IT implementation in Bengaluru. The governance procedure requires clinical staff to sign off on all UI changes. Developers are frustrated because sign-offs take 5 business days. What should Meera do?
Show Answer
Review whether the procedure can include a fast-track pathway for minor UI adjustments while retaining full sign-off for major changes — governance procedures should enable delivery, not just control it.
Balance control with delivery speed
critical-thinking
A project needs to procure 50 identical servers. The PM is deciding between one supplier (volume discount, single point of contact) and two suppliers (redundancy, competitive pressure). What factors should the PM weigh?
Show Answer
Cost savings from volume discount vs. supply chain resilience, vendor lock-in risk, single-point-of-failure risk, administrative overhead of managing two vendors, and organizational risk tolerance
Procurement strategy is a trade-off between efficiency and resilience
critical-thinking
A project's quality management plan specifies a maximum defect rate of 2 per 1000 lines of code. During testing of a 15,000-line module, the team finds 48 defects. What is the defect rate and does it meet the quality standard?
Show Answer
48 / 15 = 3.2 defects per 1000 lines. This EXCEEDS the maximum of 2 per 1000, so it does NOT meet the quality standard. The module requires defect remediation before delivery
Divide total defects by (total lines / 1000) to get defects per 1000 lines
Who does the work in a RACI?
Show Answer
Responsible (R). Can be multiple people.
R is the doer
Governance
What is the primary purpose of a project governance structure?
Show Answer
To provide a framework of accountabilities, decision-making rights, and oversight mechanisms that ensure the project delivers intended value to stakeholders while managing risks appropriately.
Think about accountability and decision rights
Equipment costs INR 6,07,000. Straight-line over 2 years, salvage INR 30,350. Annual depreciation?
Show Answer
(6,07,000 - 30,350) / 2 = INR 2,88,325 per year.
Depreciation = (cost - salvage) / useful life
Risk Management
What is the relationship between sustainability risk and long-term project viability?
Show Answer
Unsustainable project practices create long-term viability risks — environmental damage can trigger regulatory action, community backlash can halt operations, and resource depletion can make the project's benefits unsustainable. Sustainability risk management protects the project's long-term value proposition.
Sustainability risk = long-term viability risk
Dominant stakeholders have?
Show Answer
Power + Legitimacy. High authority but not urgent.
Strong formal position
Investment: INR 4,58,000. Returns: INR 5,40,440. ROI?
Show Answer
(5,40,440 - 4,58,000) / 4,58,000 x 100 = 18%.
ROI = (gain - cost) / cost x 100
critical-thinking
During strategy development, the PM identifies that two competing technologies could satisfy the project need. One is cheaper but less proven; the other is expensive with strong vendor support. Which factor should carry the MOST weight in the recommendation?
Show Answer
The technology's ability to meet the project's critical success criteria and deliver the required business value within acceptable risk levels
Use the project's agreed success criteria and risk tolerance to compare cost and capability.
What is a Pareto chart?
Show Answer
A bar chart showing defect frequency by category, ordered from most to least frequent.
80/20 rule visualization
Stakeholder provides conflicting feedback. What should the PM do?
Show Answer
Clarify the underlying needs and decision authority, facilitate discussion to align expectations, and document the agreed resolution. Escalate unresolved decisions through the appropriate governance path.
Understand and align the needs behind conflicting feedback.
Sprint velocity dropped. What should the PM do?
Show Answer
Facilitate retrospective to understand causes and identify improvements.
Learn, do not blame
critical-thinking
An organization's lessons learned repository shows that 7 out of 10 vendor-delayed projects experienced schedule overruns averaging 45 days. A PM is about to select a new vendor for a similar scope. What should the PM do?
Show Answer
Incorporate the historical vendor-delay pattern into the schedule risk analysis and negotiate contract terms that include liquidated damages for late delivery
Historical risk patterns must inform current planning and contract negotiations
Compliance
A project tracks 50 compliance requirements. At the midpoint, 40 are fully compliant, 5 have minor gaps being remediated, and 5 have major gaps. What is the overall compliance rate?
Show Answer
The fully compliant rate is 80% (40/50). Report the remaining 20% separately: 10% with minor gaps and 10% with major gaps. Also identify the status of each mandatory requirement; a favorable aggregate cannot override an unmet prerequisite.
80% compliant, 10% minor gaps, 10% major gaps
Benchmarking is?
Show Answer
Comparing processes or performance against best practices to identify improvement opportunities.
Learn from the best
Team development stages: storming requires?
Show Answer
Facilitation, patience, conflict management, and trust building from the leader.
Facilitate constructive conflict
Risk Management
What is risk tolerance and how should it influence risk communication?
Show Answer
Risk tolerance is the acceptable level of variation the organization will accept. Risk communication should report risks in the context of organizational tolerance — a risk that exceeds tolerance requires immediate escalation, while risks within tolerance may need only monitoring.
Tolerance = the line between watch and act
Dangerous stakeholders have?
Show Answer
Power + Urgency but no Legitimacy. Can cause harm.
Need careful management
Governance
What governance policy is most directly related to preventing nepotism in project team selection?
Show Answer
Conflict of interest and procurement ethics policy — it should require declaration of relationships with candidates, establish independent selection panels, and define consequences for violations.
Anti-nepotism = conflict of interest policy
critical-thinking
What is the difference between total float and free float?
Show Answer
Total float is the amount of time an activity can be delayed without delaying the project finish date; free float is the amount of time an activity can be delayed without delaying the early start date of any successor activity
Total float considers the project end; free float considers only the next activity
critical-thinking
What is resource management planning and what does it cover?
Show Answer
The process of determining what resources (human, material, equipment, facilities) are needed, when they are needed, in what quantities, and how they will be acquired, allocated, and managed throughout the project
Resource planning ensures the right resources are available at the right time
What is a project charter?
Show Answer
A formal document authorizing the project and providing the PM with authority to apply resources.
Formal authorization
INR 2,75,000 invested at 5% for 2 years. Future value?
Show Answer
FV = 2,75,000 x (1.05)^2 = INR 3,03,188.
FV = PV x (1+r)^n
A change to cost baseline requires?
Show Answer
Use the established change-control process, including updated estimates and integrated impact analysis, and obtain the approval required by the defined authority. Update the affected authorized cost baseline and records.
Follow the defined authority and update affected authorized records
Risk Management
What is the difference between qualitative and quantitative risk analysis?
Show Answer
Qualitative analysis assesses risks using descriptive scales (high/medium/low probability and impact) to prioritize them. Quantitative analysis uses numerical analysis (Monte Carlo simulation, sensitivity analysis, decision trees) to numerically estimate overall project risk exposure.
Qualitative = rank; Quantitative = number
Appraisal costs include?
Show Answer
Inspection, testing, audits, reviews.
Cost of checking quality
Negative stakeholders are?
Show Answer
Stakeholders who oppose the project or perceive its outcomes as adversely affecting their interests. Understand their concerns and engage them respectfully.
Understand the reasons for opposition
Conflict resolution: when to escalate?
Show Answer
When parties cannot reach resolution, when it blocks critical activities, or when policies are violated.
Know when to step in
Change Management
A ₹3 crore project receives approval for a change that increases the budget by 15%. After implementation, the team discovers the change requires an additional 20% due to unforeseen technical dependencies. What should the PM do?
Show Answer
Assess the newly discovered dependencies, forecast cost and schedule impacts, and confirm whether authorized reserves can cover the response. Submit a change request where additional funding, baseline changes, or scope changes require approval; do not exceed delegated authority.
Assess the variance and use the required approval route
Change control system is?
Show Answer
A documented set of procedures defining how changes are submitted, evaluated, approved, and tracked.
Formal change procedure
What is a management reserve?
Show Answer
Budget or time reserved for unknown-unknowns. Controlled by senior management.
Unknown risks
critical-thinking
What is the difference between maintaining the project management plan and updating it due to approved changes?
Show Answer
Maintaining the plan is the continuous monitoring and administrative upkeep (e.g., updating actual dates, tracking against milestones), while updates from approved changes result from formal change control decisions that alter baselines or subsidiary plans
Maintenance is routine; changes are triggered by formal decisions
critical-thinking
During resource optimization, the PM discovers that the team's peak workload coincides with the organization's annual performance review cycle (3 weeks). Team members typically take 20-30% more leave during this period. How should the PM account for this?
Show Answer
Use the actual expected absences and productive hours to update the resource calendar and capacity forecast. Shift work or negotiate adjustments if the resulting capacity is insufficient; the reported increase in leave alone does not establish a 20-25% capacity reduction.
Calculate capacity from available hours and actual absences.
critical-thinking
Suresh has a well-defined WBS with 28 work packages. Each package owner has provided detailed estimates. The total aggregated estimate is 1,200 person-hours. Which estimating approach did Suresh most likely use?
Show Answer
Bottom-up estimating, since individual work packages were estimated in detail and then aggregated
Individual package estimates that are aggregated = bottom-up
Issue Management
A PM faces two simultaneous issues: (A) a regulatory fine threat requiring legal expertise, and (B) a server outage requiring technical expertise. With only one specialist available, how should the PM prioritize intervention?
Show Answer
Assess which issue has the most severe consequences and shortest resolution window. Regulatory fines often have hard deadlines and severe penalties — issue A may need the legal specialist first, while the technical issue may have a temporary workaround.
Severity + deadline determine priority
Change Management
A PM implements a change but forgets to update the requirements traceability matrix. What risk does this create?
Show Answer
Requirements drift — the RTM no longer accurately maps requirements to design, test cases, and deliverables. Future testing, compliance audits, and change impact assessments will be unreliable, potentially missing requirement gaps or conflicts.
RTM must stay synchronized with changes
critical-thinking
Using three-point estimating with a triangular distribution: Activity A has an optimistic estimate of 4 days, most likely of 6 days, and pessimistic of 14 days. What is the expected duration?
Show Answer
(4 + 6 + 14) / 3 = 8 days
Triangular distribution: (O + M + P) / 3 (vs PERT which is (O + 4M + P) / 6)
critical-thinking
Priya plans to use Six Sigma for her manufacturing quality project and Agile retrospectives for her software quality project. Is this appropriate?
Show Answer
Yes — quality methods should be selected based on the project type, industry context, and organizational standards. Six Sigma is appropriate for manufacturing process control; Agile retrospectives are appropriate for iterative software improvement
Quality methods are not one-size-fits-all — they must match the project context
critical-thinking
At the project midpoint, the PM notices the contingency reserve is 60% unused while the management reserve has been untouched. What should the PM consider?
Show Answer
Whether the risk assessment was overly conservative (contingency overestimated) or whether risks have not materialized as expected — excess contingency may be reduced through formal change control with stakeholder approval
Unused reserves should be evaluated — they may indicate risk assessment errors or genuine favorable conditions
critical-thinking
The customer signs off on the scope statement but later claims they assumed certain features were included that were not documented. The PM had sent the scope statement 3 times with no response until the last reminder. What should the PM's defense be?
Show Answer
Review the signed scope, requirements traceability, and relevant agreements with the customer to clarify the discrepancy. Explain the agreed baseline and assess the requested features through the applicable approval process, rather than treating sign-off as a substitute for resolving expectations.
Use documented agreement to clarify scope and collaboratively resolve unmet expectations.
INR 1,06,000 needed in 3 years at 10% discount. Present value?
Show Answer
PV = 1,06,000 / (1.10)^3 = INR 79,639.
PV = FV / (1+r)^n
Situational leadership vs Tuckman?
Show Answer
Tuckman is about team maturity over time. Situational is about adapting leadership style to individual readiness.
Different but related
Critical deliverable is found non-compliant late. What should the PM do?
Show Answer
Record and assess the nonconformance, involve the responsible team or supplier as applicable, and arrange correction or authorized disposition. Contain affected work where necessary and assess schedule, cost, safety, and acceptance impacts.
Address nonconformance through the applicable quality and compliance process.
PM needs to estimate without enough information. What should they do?
Show Answer
Explain the uncertainty and assumptions, use suitable expert judgment or comparable historical data if available, and present an appropriate estimate range. Refine the estimate as information improves.
Select an estimation method that fits the information actually available.
critical-thinking
A project needs a data scientist for months 3-6. No data scientists are available internally. The PM considers hiring a contractor. What should the PM evaluate?
Show Answer
Contractor availability timeline, cost compared to internal hire, knowledge transfer requirements, data security considerations, and exit/knowledge capture plan
External resources require additional planning for onboarding, security, and knowledge transfer
Who receives updates in a RACI?
Show Answer
Informed (I). Kept up to date on relevant progress, decisions, and results through one-way communication.
I is kept informed
Change request would improve quality but extend the schedule. What should the PM do?
Show Answer
Assess integrated impacts and present the trade-offs to the authority defined in the change-control plan. Approve only within documented delegation, and otherwise obtain the required approval before updating affected baselines.
Evaluate trade-offs and respect delegated authority
Path A(4d)->B(19d)->C(5d) = 28 days. Path A(4d)->D(8d) = 12 days. Total float on second path?
Show Answer
16 days of total float.
Total float = critical path - alternative path
Equipment costs INR 6,23,000. Straight-line over 9 years, salvage INR 99,680. Annual depreciation?
Show Answer
(6,23,000 - 99,680) / 9 = INR 58,147 per year.
Depreciation = (cost - salvage) / useful life
Change request is rejected. What should happen to the requester?
Show Answer
The requester should be informed of the rationale. Do not let rejection damage the relationship.
Transparency builds trust
Compliance
What is the risk of identifying compliance requirements too late in a project?
Show Answer
Late identification typically requires redesign, rework, or retrofit of already-built components, leading to cost overruns, schedule delays, and potentially inability to meet mandatory requirements. In regulated industries, this can mean project failure.
Late compliance = expensive rework
Hybrid team management challenges?
Show Answer
Mixed in-person/remote creates proximity bias, information asymmetry, and coordination complexity.
Hybrid creates invisible asymmetries
critical-thinking
What is the critical path method (CPM) in schedule management?
Show Answer
A technique that identifies the longest sequence of dependent activities in a project schedule, determining the minimum possible project duration; any delay on the critical path directly delays the project completion date
In an unconstrained CPM network, the critical path normally has zero total float; imposed dates can alter the float values.
Original estimates were not data-driven. What should the PM do?
Show Answer
Re-estimate using data-driven techniques and update the plan.
Data beats intuition
critical-thinking
What are quality requirements in project management?
Show Answer
The specific quality standards, criteria, and specifications that the project's deliverables must meet, including performance metrics, compliance standards, customer expectations, and regulatory requirements
Quality requirements define 'how good' the deliverable must be
INR 2,89,000 needed in 7 years at 5% discount. Present value?
Show Answer
PV = 2,89,000 / (1.05)^7 = INR 2,05,387.
PV = FV / (1+r)^n
PM needs to say no to a stakeholder. What should they do?
Show Answer
Explain why, reference the plan, and offer alternatives.
No with respect and alternatives
critical-thinking
Karthik's organization mandates that all project schedules use the standard template which includes 8 mandatory reporting milestones. Karthik's small project only needs 3 milestones. What should Karthik do?
Show Answer
Discuss proportionate tailoring with the PMO and obtain an authorized exception for any mandatory milestone that is not applicable. Document the approved rationale and retain required milestones unless the policy permits their removal.
Tailoring must respect mandatory organizational controls.
critical-thinking
What is effort estimation in project management?
Show Answer
The process of predicting the amount of person-hours or person-days of work required to complete project activities, distinct from duration which is measured in calendar time
Effort measures work input; duration measures elapsed time
Change Management
What information should a change status communication include?
Show Answer
Change request ID, description, current status (submitted/under review/approved/rejected/implemented), impact summary, decision authority, timeline, and any actions required from stakeholders.
ID, description, status, impact, decision, timeline
Compliance
A GDPR-covered project transfers personal data from the EEA to servers in India without a required transfer mechanism. What consequences should the PM assess?
Show Answer
Assess the transfer noncompliance with qualified privacy and legal specialists, including possible enforcement, financial penalties, required remediation, and operational or reputational effects. Separately determine whether a personal-data breach has occurred and whether the legal notification criteria and deadlines apply; an unlawful transfer alone does not establish that duty.
Distinguish transfer noncompliance from a reportable data breach
Path A(20d)->B(7d)->C(3d) = 30 days. Path A(20d)->D(14d) = 34 days. Total float on second path?
Show Answer
0 days of total float on the second path. It is the critical path at 34 days; the 30-day first path has 4 days of path float under the stated simple network.
Identify the longest path first; negative float requires an unmet date constraint.
Compliance
What is a compliance threat?
Show Answer
Any condition, event, or action that could cause the project to fail to meet a compliance requirement, resulting in legal penalties, financial losses, reputational damage, or operational disruption.
Threats = things that cause non-compliance
Risk Management
A tornado diagram for a construction project shows that 'soil contamination remediation' has the widest bar. What does this mean?
Show Answer
Within the modeled input ranges, soil-contamination remediation has the largest effect on the selected cost or schedule output. Use that sensitivity alongside probability, urgency, assumptions, and response options when prioritizing risk treatment.
Widest bar = greatest modeled output sensitivity
PM discovers a shortcut that would save time but has risks. What should they do?
Show Answer
Evaluate the shortcut's feasibility, risk, quality, compliance, and schedule effects with the relevant experts. Present the options to the authorized decision-maker and obtain approval where required.
Risk acceptance must respect decision authority and mandatory requirements.
PV = INR 24,000, EV = INR 45,000. SPI?
Show Answer
SPI = 45,000 / 24,000 = 1.88. Ahead of schedule.
SPI = EV / PV. < 1 means behind.
Change in evaluation. Requestor asks for timeline. What should the PM communicate?
Show Answer
Status, expected decision timeline, and the evaluation owner.
Status updates are not decisions
Change Management
A project's change log shows 40 changes in the last quarter, but the PM's status reports to the steering committee only mention 'ongoing change management.' What communication problem exists?
Show Answer
The PM is not effectively communicating change control status — the steering committee needs visibility into change volume, impact, trend analysis, and aggregate cost/schedule implications to make informed governance decisions.
Governance needs aggregate change intelligence
critical-thinking
The PM is designing a delivery solution for a data migration project where the source system will be decommissioned 3 months after go-live. What critical factor must the delivery solution address?
Show Answer
Data verification and knowledge transfer requirements after go-live, including a warranty period for data accuracy verification and a support handover plan before the source system is decommissioned
Delivery solutions must cover the full lifecycle including post-delivery transition and knowledge transfer
Risk Management
A tech startup in Bengaluru is launching a new SaaS product. Which risk identification technique is most likely to surface competitive and market risks?
Show Answer
SWOT analysis can help: strengths and weaknesses examine internal conditions, while opportunities and threats examine the external environment. Combine it with market information and expert input to identify actionable competitive and market risks.
SWOT combines internal and external perspectives
Governance
What is an escalation path in project governance?
Show Answer
A predefined, documented process for routing issues and decisions upward through the organizational hierarchy when they cannot be resolved at the current level, including who to escalate to, within what timeframe, and what information to include.
Escalation = going up the chain when stuck
critical-thinking
Vendor S has delivered 3 of 5 milestones on time. The 4th milestone is 10 days late with no communication. The PM calls and the vendor says they found a technical issue. What should the PM do?
Show Answer
Document the late delivery, request a recovery plan from the vendor with a new date, assess the impact on the project, and issue a formal deficiency notice per the contract terms
Late delivery without communication is a contract violation that must be formally documented
Minor typo in a report. Does this need formal change control?
Show Answer
Depends on the impact. Trivial changes within tolerance may not need CCB approval.
Not all changes need CCB
Risk Management
A risk register shows: Risk R-017, 'key developer resignation,' probability 30%, impact high, response: 'cross-train two team members,' contingency: 'hire contractor within 2 weeks,' trigger: 'developer submits resignation.' What does the contingency plan address?
Show Answer
The contractor plan is an agreed contingent response activated when the developer submits a resignation. Cross-training reduces the potential impact of the departure and may still be effective. A fallback plan is a further response used if the selected response proves inadequate.
Contingency acts on its trigger; fallback addresses an inadequate response
Risk Management
What are five common response strategies for threats?
Show Answer
Avoid the threat; mitigate its probability or impact; transfer defined exposure to another party; accept it, either passively with monitoring or actively with appropriate contingency; or escalate it when it exceeds project scope or authority. Choose a response suitable for the risk and governing obligations.
Avoid, mitigate, transfer, accept, escalate
What is a Gantt chart?
Show Answer
A bar chart showing project activities over time.
Visual timeline
Backlog = 415 points, velocity = 50 points/sprint. How many sprints?
Show Answer
415 / 50 = 8.3. Round up to 9 sprints.
Sprints = ceiling(backlog / velocity)
INR 88,000 needed in 6 years at 5% discount. Present value?
Show Answer
PV = 88,000 / (1.05)^6 = INR 65,667.
PV = FV / (1+r)^n
How should resistance to change be managed?
Show Answer
Understand the causes of resistance and the effects of the change, involve affected people, communicate its purpose, and provide suitable participation, training, support, and feedback. Coordinate legitimate constraints and decisions with the organizational change owners; there is no universal sequence requiring manipulation or coercion.
Assess the reasons for resistance and support adoption
PM discovers ethics violations by a team member. What should they do?
Show Answer
Follow organizational policy. Document, report, protect stakeholders.
Ethics violations are serious
critical-thinking
What does maintaining the project management plan mean?
Show Answer
The ongoing process of monitoring, controlling, and updating the plan throughout the project to reflect approved changes, actual performance data, and evolving project circumstances
The plan is not static — it evolves with the project through integrated change control
critical-thinking
During supplier management, the PM discovers that the vendor is using substandard materials that do not meet contract specifications but pass initial inspection. What should the PM do?
Show Answer
Verify the nonconformance, document it, and require corrective action under the contract's quality provisions. Apply payment withholding or other remedies only as permitted by the contract and the organization's authorized procurement process.
Use the applicable contractual remedies and approval authority.
What does the Planning process group accomplish?
Show Answer
It establishes scope and objectives and develops the coordinated course of action needed to achieve them, with progressive elaboration as appropriate.
Planning is revisited as more information becomes available.
critical-thinking
What is a schedule management plan and what does it define?
Show Answer
A component of the project management plan that establishes the criteria and activities for developing, monitoring, controlling, and managing the project schedule, including how schedule changes will be managed
It is the governance framework for all schedule-related decisions throughout the project
What is TKI (Thomas-Kilmann)?
Show Answer
Five conflict-handling modes: Competing, Collaborating, Compromising, Avoiding, Accommodating.
Five modes based on assertiveness and cooperativeness
Organizational process assets (OPAs) include?
Show Answer
Processes, procedures, templates, historical information, lessons learned, knowledge bases.
Resources the organization already has
Governance
A project uses a steering committee, a project board, and an operational team. What is the primary role of the steering committee?
Show Answer
To provide strategic oversight, approve major decisions, resolve escalated issues beyond the project manager's authority, and ensure alignment with organizational strategy.
Steering = strategic direction
critical-thinking
A project has Activity A (4 days) followed by Activity B (6 days) with a Finish-to-Start relationship and 2 days of lag. What is the total elapsed time from the start of A to the finish of B?
Show Answer
4 days (A) + 2 days (lag) + 6 days (B) = 12 days
FS with lag: Predecessor finish + lag + Successor duration
Investment: INR 4,02,000. Annual benefit: INR 94,000 for 3 years at 10%. NPV?
Show Answer
Total PV of benefits: INR 2,33,764. NPV = 2,33,764 - 4,02,000 = INR -1,68,236. Project is not viable at this rate.
NPV = PV of benefits - PV of costs
Issue Management
An issue requires a decision that affects multiple stakeholders with competing interests. What structured approach should the PM use?
Show Answer
Facilitate a decision-making workshop using multi-criteria decision analysis (MCDA) — define evaluation criteria, weight them, score each option, and present the analysis. This depersonalizes the decision and makes the rationale transparent to all parties.
MCDA = structured, transparent decision-making
PERT: optimistic=2, most likely=2, pessimistic=3. Expected duration?
Show Answer
(2 + 4x2 + 3) / 6 = 2.17 days.
PERT = (O + 4M + P) / 6
critical-thinking
Deepa has completed all subsidiary plans for her INR 8 crore construction project. Before seeking baseline approval, she reviews the cost management plan and notices it references a currency that does not match the project's funding currency. What should Deepa do?
Show Answer
Update the cost management plan to reflect the correct currency and re-verify all subsidiary plans for consistency before proceeding with baseline approval
An inconsistency in one plan indicates possible errors in others — fix and re-verify
What is a control chart?
Show Answer
A chart monitoring process stability over time against control limits.
Statistical process control
Compliance
A compliance officer warns that the project's cloud architecture may violate an applicable Indian sector-specific data localization rule. What should the PM do FIRST?
Show Answer
Confirm the rule's applicability and effective date with qualified compliance and legal specialists, then assess affected data flows, architecture gaps, and remediation options before authorizing design changes.
Verify the specific applicable localization rule
Investment: INR 2,34,000. Returns: INR 2,76,120. ROI?
Show Answer
(2,76,120 - 2,34,000) / 2,34,000 x 100 = 18%.
ROI = (gain - cost) / cost x 100
What is crashing?
Show Answer
Adding resources to critical path activities to shorten the schedule at additional cost.
Cost for speed
INR 2,83,000 invested at 8% for 6 years. Future value?
Show Answer
FV = 2,83,000 x (1.08)^6 = INR 4,49,085.
FV = PV x (1+r)^n
PM needs to build consensus among stakeholders. What should they do?
Show Answer
Use facilitated workshops, seek common ground, build from agreement upward.
Facilitation, not dictatorship
critical-thinking
Rajesh is estimating a machine installation activity. He polls 5 team members: 3 say 5 days, 1 says 4 days, 1 says 7 days. Rajesh decides to use 5 days. What estimation technique is he using?
Show Answer
Expert judgment (consensus or individual expert opinion), though he could also consider using a more formal technique like PERT to account for the uncertainty
Individual or panel expert judgment is a valid technique but may not capture uncertainty
Equipment costs INR 7,88,000. Straight-line over 8 years, salvage INR 55,160. Annual depreciation?
Show Answer
(7,88,000 - 55,160) / 8 = INR 91,605 per year.
Depreciation = (cost - salvage) / useful life
critical-thinking
The PM wants to use INR 5 lakh from management reserve to cover a cost overrun. The PMO says management reserve is only for unknown risks, and the overrun was from a known risk that was poorly managed. What is the correct response?
Show Answer
The PM must cover the overrun from the project's contingency reserve or propose a formal budget increase through change control — management reserve is not for compensating poor risk management
Management reserve is for unplanned events, not for compensating failure to manage known risks
Customer keeps changing acceptance criteria. What should the PM do?
Show Answer
Document changes, assess impact, and apply formal change control.
Formalize every change
Delegating (situational leadership)?
Show Answer
Low directive, low supportive. For high competence, high commitment.
Turn over responsibility
Risk A has 30% probability with INR 50,000 impact. Risk B has 15% probability with INR 80,000 impact. Which has higher EMV?
Show Answer
A: 0.30 x 50,000 = INR 15,000. B: 0.15 x 80,000 = INR 12,000. Risk A has higher EMV.
EMV = probability x impact
What are the ten knowledge areas used in the PMBOK Guide Sixth Edition?
Show Answer
Integration, Scope, Schedule, Cost, Quality, Resource, Communications, Risk, Procurement, Stakeholder.
These organize predictive practices; the July 2026 PMP ECO uses domains, tasks, and enablers.
Risk Management
A risk audit reveals that 60% of identified risks have no documented response. The PM had delegated response planning to team leads who did not complete it. What should the PM do?
Show Answer
Immediately assign response owners to all unaddressed risks, set a deadline for response plans, report the gap to the sponsor as a governance issue, and implement a risk review process to prevent recurrence.
Unaddressed risks = time bombs
Investment: INR 3,81,000. Returns: INR 4,45,770. ROI?
Show Answer
(4,45,770 - 3,81,000) / 3,81,000 x 100 = 17%.
ROI = (gain - cost) / cost x 100
Issue Management
A server outage has stopped development work for 2 days. The PM must evaluate impact. What dimensions should be assessed?
Show Answer
Schedule impact (delay to milestones), cost impact (idle resources, potential penalties), scope impact (features that cannot be completed), quality impact (rushed work to catch up), and stakeholder impact (client communication, reputation).
Schedule, cost, scope, quality, stakeholder
Equipment costs INR 5,03,000. Straight-line over 2 years, salvage INR 80,480. Annual depreciation?
Show Answer
(5,03,000 - 80,480) / 2 = INR 2,11,260 per year.
Depreciation = (cost - salvage) / useful life
critical-thinking
A known risk (supplier delay) materializes and costs INR 12 lakh. The PM's contingency reserve for this risk was INR 10 lakh. What is the correct process?
Show Answer
The PM uses the INR 10 lakh contingency, then submits a change request for the remaining INR 2 lakh, which could come from management reserve or require scope/budget adjustment
Contingency is used first; any shortfall requires a formal request for additional funds
Issue Management
A risk's trigger condition occurs but the risk event has not yet impacted the project. Is it a risk or an issue?
Show Answer
Determine whether the trigger is an early warning or evidence that the event has occurred. If the event remains uncertain, monitor and execute the agreed trigger-based response. If the event or current condition exists, manage it as an issue and activate applicable authorized responses, even before every consequence is known.
Check event occurrence; the trigger alone is not the definition
critical-thinking
What are the three main contract types in PMP and how does risk allocation differ between them?
Show Answer
The main families are fixed-price, cost-reimbursable, and time and materials. Fixed-price places more defined-scope cost risk on the seller; cost-reimbursable places more cost risk on the buyer; T&M combines agreed unit rates with variable quantities, so the buyer needs oversight and suitable cost limits.
CPFF is one cost-reimbursable subtype; assess risk from the actual terms.
What is a milestone?
Show Answer
A significant point or event in the project with zero duration.
Zero duration = milestone
What is strategic alignment?
Show Answer
The degree to which project outcomes support organizational strategy.
Projects should serve strategy
Business case is no longer valid. What should the PM do?
Show Answer
Reassess the remaining costs, risks, and achievable value with the sponsor or authorized governance body. Present options to revise, pause, or terminate; further work must have a justified and authorized basis.
Continuation is an authorized value decision; sunk costs do not justify it.
Issue Management
A key stakeholder stops responding to communications during a critical approval phase. The PM cannot get sign-off needed to proceed. What is the primary impact?
Show Answer
Schedule impact through blocked milestone — without the stakeholder's approval, the project cannot proceed to the next phase regardless of team readiness. Secondary impacts include team demotivation and potential rework if approval comes late.
Blocked stakeholder = blocked schedule
critical-thinking
A project spends INR 4 lakh on quality training (prevention), INR 3 lakh on testing (appraisal), INR 6 lakh on rework (internal failure), and INR 12 lakh on customer complaints and returns (external failure). What is the total cost of quality and what percentage is external failure?
Show Answer
Total CoQ = 4+3+6+12 = INR 25 lakh. External failure percentage = 12/25 = 48%
A high external-failure share warrants root-cause analysis and evaluation of preventive controls.
Customer wants daily detailed reports. What should the PM do?
Show Answer
Clarify the customer's decisions and reporting obligations, then agree a useful level of detail and cadence. Use dashboards or detailed reports as appropriate and document the agreement in the communication strategy.
Agree reporting that meets the stakeholder's actual needs.
Who provides input in a RACI?
Show Answer
Consulted (C). Two-way communication.
C is consulted before decisions
critical-thinking
Given the following activities and dependencies: A(3d) FS B(5d) FS C(4d), B FS D(2d), C FS D. What is the critical path and total project duration?
Show Answer
The links require A before B, B before C, and C before D; D also depends on B. The critical path is A-B-C-D = 3 + 5 + 4 + 2 = 14 days. The B-D link does not remove D's dependency on C.
Follow every stated predecessor relationship when constructing the network.
PERT: optimistic=3, most likely=8, pessimistic=40. Expected duration?
Show Answer
(3 + 4x8 + 40) / 6 = 12.50 days.
PERT = (O + 4M + P) / 6
critical-thinking
Arun is told by the sponsor that the project MUST be completed by March 31, 2027 for fiscal year reporting. Arun knows the realistic completion date is June 2027. What should Arun classify this sponsor directive as?
Show Answer
A hard constraint that must be documented in the project management plan, then analyzed for feasibility — if infeasible, escalate to the sponsor with supporting data
A sponsor mandate is a constraint, not a target — it must be documented and its feasibility assessed
Two changes: one saves INR 50,000 but adds 2 weeks. Another costs INR 30,000 but saves 1 week. How should they be evaluated?
Show Answer
Evaluate against project objectives, constraints, and stakeholder priorities. Use weighted scoring.
Evaluate against objectives
Transformational leadership emphasizes?
Show Answer
Inspiring and motivating through vision, charisma, and intellectual stimulation.
Vision-driven
critical-thinking
Karthik needs 3 senior Java developers for 6 months and 2 QA engineers for 3 months. His organization has only 2 senior Java developers available in that timeframe. What should Karthik do?
Show Answer
Document the resource gap in the resource management plan, escalate to functional managers for resource negotiation, and identify alternatives (hire, contract, or adjust the schedule)
Resource gaps must be escalated early — they cannot be solved at the last minute
What is a decision tree analysis?
Show Answer
A diagram mapping decisions and their possible consequences including expected monetary value.
Decision path analysis
Investment: INR 3,00,000. Annual benefit: INR 40,000. Simple payback period?
Show Answer
3,00,000 / 40,000 = 7.5 years.
Simple payback = investment / annual benefit
Who approves a change request?
Show Answer
The appropriate change control authority (CCB, PM, sponsor, or other role defined in the project).
Depends on change type and magnitude
Change Management
What is the change control process in project management?
Show Answer
A structured workflow for requesting, evaluating, approving, implementing, and verifying changes to project scope, schedule, cost, or quality. It ensures that all changes are assessed for impact, approved by appropriate authority, and properly documented.
Change control = gate every change
Compliance
What are common compliance methods used in project management?
Show Answer
Audits and inspections, control self-assessment, automated compliance monitoring tools, control testing, policy enforcement checklists, continuous control monitoring (CCM), and compliance dashboards integrated into project reporting.
Audits, self-assessments, and automated tools
Path A(13d)->B(20d)->C(4d) = 37 days. Path A(13d)->D(14d) = 27 days. Total float on second path?
Show Answer
10 days of total float.
Total float = critical path - alternative path
critical-thinking
Rajesh has completed the scope statement and WBS for his warehouse automation project. The operations manager refuses to sign off, claiming the WBS does not include warehouse layout modification. Rajesh believes layout modification is out of scope. What should Rajesh do?
Show Answer
Schedule a scope alignment meeting to clarify assumptions, review the project charter, and negotiate whether layout modification should be added via a formal change request or remain out of scope
Disagreement on scope must be resolved through discussion, not by unilaterally deciding
critical-thinking
How do contingency and management reserves relate to the cost baseline and total project budget?
Show Answer
Contingency reserve is included in the cost baseline for identified uncertainty. Management reserve is outside the cost baseline but part of the total project budget. Authorized use of management reserve for project work requires appropriate approval and a baseline update.
Cost baseline includes contingency; total budget also includes management reserve.
PM has to choose between two equally good approaches. What should they do?
Show Answer
Evaluate with the team, document decision rationale, proceed.
Decision record matters
Equipment costs INR 2,69,000. Straight-line over 2 years, salvage INR 18,830. Annual depreciation?
Show Answer
(2,69,000 - 18,830) / 2 = INR 1,25,085 per year.
Depreciation = (cost - salvage) / useful life
critical-thinking
What is the purpose of the communications management plan in financial reporting?
Show Answer
To define who receives financial reports, what information they receive, the format and frequency of reports, and the escalation paths for financial exceptions
Financial information is only useful if it reaches the right stakeholders in the right format at the right time
Backlog = 435 points, velocity = 17 points/sprint. How many sprints?
Show Answer
435 / 17 = 25.6. Round up to 26 sprints.
Sprints = ceiling(backlog / velocity)
What does the Closing process group accomplish?
Show Answer
It formally completes or terminates a project or phase and concludes the applicable closure activities.
Close authorized work and outstanding obligations.
Coaching in Blanchard's SLII model?
Show Answer
High directive, high supportive. For disillusioned learners with low to some competence and low commitment on the specific task.
Guide the task and rebuild commitment
Issue Management
Two stakeholders have conflicting requirements for the same deliverable. The PM resolves it by choosing the more powerful stakeholder's requirement. What governance issue does this create?
Show Answer
Decision bias — the PM should use objective criteria (business case alignment, feasibility, compliance requirements) rather than stakeholder power dynamics. Documenting the decision rationale protects the project and ensures fairness.
Objective criteria > power dynamics
PV = INR 60,000, EV = INR 31,000. SPI?
Show Answer
SPI = 31,000 / 60,000 = 0.52. Behind schedule.
SPI = EV / PV. < 1 means behind.
critical-thinking
What does 'value-based delivery' mean in project management?
Show Answer
Delivering project outcomes that create measurable value for the customer and organization, rather than simply completing a set of defined tasks or deliverables within constraints
Value delivery focuses on outcomes and benefits, not just outputs
Change Management
What is the difference between a change request and a change order?
Show Answer
A change request is an initial proposal that describes the desired change and its justification. A change order is an approved, binding authorization to implement the change, including the revised scope, cost, schedule, and any other affected baselines.
Request = proposal; Order = authorization
PERT: optimistic=3, most likely=9, pessimistic=36. Expected duration?
Show Answer
(3 + 4x9 + 36) / 6 = 12.50 days.
PERT = (O + 4M + P) / 6
What is a project management plan?
Show Answer
The document describing how the project will be executed, monitored, and controlled.
The "how" document
Issue Management
A dashboard shows 30 open issues but the PM has not updated the issue log in 2 weeks. The steering committee is asking for a status report. What should the PM do FIRST?
Show Answer
Immediately update the issue log — assess each open issue's current status, priority, and resolution progress. Without current data, any status report will be inaccurate and undermine governance credibility.
Current data before reporting
Investment: INR 3,84,000. Annual benefit: INR 1,00,000 for 6 years at 8%. NPV?
Show Answer
Total PV of benefits: INR 4,62,288. NPV = 4,62,288 - 3,84,000 = INR 78,288. Project is financially viable.
NPV = PV of benefits - PV of costs
Change Management
A project has 23 open change requests ranging from minor text updates to major feature additions. How should the PM communicate change status to stakeholders?
Show Answer
Tier the communication: executive dashboard showing count, total value, and RAG status; CCB getting detailed status on each request; requestors getting individual updates on their specific changes. Avoid overwhelming executives with operational detail.
Different audiences, different detail levels
For an ideal centered Six Sigma process before the conventional long-term mean shift, how far is each specification limit from the mean?
Show Answer
Six short-term standard deviations from the mean. The commonly quoted 3.4 DPMO convention additionally assumes a 1.5-sigma long-term shift.
Separate short-term specification distance from the long-term defect-rate convention.
Governance
A project governance framework requires that all change requests include a risk assessment. A PM receives a change request with only a cost estimate. What should the PM do FIRST?
Show Answer
Return the change request to the originator with the requirement for a risk assessment, explaining that this is a governance rule that must be followed before the change enters evaluation.
Follow the governance rule
SWOT Strengths/Weaknesses are?
Show Answer
Internal factors. Things the organization can control.
Internal
Path A(2d)->B(16d)->C(5d) = 23 days. Path A(2d)->D(2d) = 4 days. Total float on second path?
Show Answer
19 days of total float.
Total float = critical path - alternative path
Change Management
A change is approved and implemented but later found to have been based on incorrect data. The impact assessment used outdated market projections. Who is accountable?
Show Answer
The PM is accountable for ensuring the impact assessment used valid, current data. The CCB should verify data quality before approval. The PM should initiate a corrective change to address the error and review the impact assessment process to prevent recurrence.
PM accountable for assessment quality
Product Owner is not available. What should the PM do?
Show Answer
Escalate to management and protect the team from blocked decisions.
Team must have access to PO
critical-thinking
Nandini is developing the project management plan for a pharma manufacturing expansion. She discovers that the site requires environmental clearance under EIA 2006, which adds 90 days to the approval timeline. What should Nandini do with this information?
Show Answer
Include the required approval work and timeline in the schedule, document the constraint and dependencies, and analyze whether it lies on the critical path. Confirm the applicable requirement and schedule assumptions with responsible experts.
A required approval affects the schedule; network analysis determines whether it is critical.
What is an organizational change request?
Show Answer
A formal request to alter policies, processes, or assets that affect multiple projects or the entire organization.
Higher-level change
Salience model classifies stakeholders by?
Show Answer
Power, Legitimacy, and Urgency.
Three-dimension model (Mitchell et al.)
Stakeholder engagement means?
Show Answer
Communicating and working with stakeholders to meet their needs and expectations.
Active involvement, not just reporting
critical-thinking
A project at month 4 of 8 has: PV = INR 80 lakh, EV = INR 70 lakh, AC = INR 85 lakh. Calculate CPI, SPI, and predict whether the project will finish over or under budget at the current efficiency.
Show Answer
CPI = EV/AC = 70/85 = 0.824: each rupee spent earns about 82.4 paise of budgeted work. SPI = EV/PV = 70/80 = 0.875. Cost efficiency is unfavorable and less budgeted work is complete than planned. If current cost efficiency continues, EAC = BAC/CPI; BAC is not given, so a numeric EAC cannot be calculated.
CPI measures budgeted value earned per unit of actual cost; BAC must be supplied.
What is a histogram?
Show Answer
A bar chart showing frequency distribution of data.
Visualizes distribution
critical-thinking
A government infrastructure project in India requires a complete design before construction can begin due to regulatory compliance. The project budget is INR 120 crore with a fixed 36-month deadline. Which delivery approach is MOST appropriate?
Show Answer
Predictive (waterfall) approach, since the requirements are well-defined, regulatory constraints mandate complete design upfront, and the parameters are fixed
Regulatory requirements that mandate complete design before work begins point to a predictive approach
Change Management
When should change documentation be updated — before, during, or after change implementation?
Show Answer
Keep records current throughout: log and assess the proposal before approval, record the decision and update affected authorized planning records for implementation, track execution, then record verification and closure. Change only affected baselines through the required approval process.
Maintain the decision and implementation trail throughout
Motivation theories: McClelland?
Show Answer
Need for Achievement, Power, Affiliation. Different people are driven by different needs.
Three needs
A Scrum team wants to skip the Sprint Retrospective. What should the PM or Scrum Master do?
Show Answer
Help the team understand its purpose and facilitate a useful retrospective within its timebox. The event is a required part of Scrum and lets the team improve quality and effectiveness.
Make the required Scrum event useful for the team.
Risk Management
What is a risk register and what are its key components?
Show Answer
A document where the results of risk analysis and planning are recorded. Key components: risk ID, risk description, risk category, probability, impact, risk score, priority, risk owner, response strategy, specific actions, contingency plan, trigger conditions, and current status.
Risk ID, description, P&I, score, owner, response, actions, status
critical-thinking
Priya is creating the scope statement for a mobile banking app. The marketing team keeps adding feature requests during scope definition. What technique should Priya use to bring discipline to the process?
Show Answer
Facilitate MoSCoW prioritization (Must have, Should have, Could have, Won't have) with all stakeholders to reach consensus on what is truly in scope
MoSCoW is designed specifically to manage competing feature requests during scope definition
Contract requires formal delay notices through a named channel. Supplier discussed delay in team chat. Is that sufficient?
Show Answer
Not unless the contract recognizes that chat as the required notice. Follow the specified procedure.
Informal is not compliant
critical-thinking
Sneha's organization has completed 8 mobile app projects. The historical data shows actual durations were consistently 20-35% longer than estimated durations due to integration testing underestimation. Sneha is now estimating a similar app. What should she do?
Show Answer
Analyze actual integration-testing effort and duration from comparable projects, identify the omitted drivers, and use adjusted estimates for the current interfaces and testing needs. Set an evidence-based risk allowance rather than automatically applying the whole-project overrun percentage to one activity.
Use comparable activity-level evidence when correcting an activity estimate.
Path A(14d)->B(19d)->C(5d) = 38 days. Path A(14d)->D(10d) = 24 days. Total float on second path?
Show Answer
14 days of total float.
Total float = critical path - alternative path
Change Management
A CCB rejects a change request that the project manager believes is essential. What should the PM do?
Show Answer
Document the CCB's decision and rationale, communicate it to the change requester, and explore whether the underlying need can be met within the current project scope through alternative approaches. Escalate only if the rejection creates a project-threatening gap.
Document, communicate, explore alternatives
critical-thinking
Meera is building a WBS for a software upgrade. She keeps decomposing deliverables until she reaches components that can each be completed in under 80 hours. Is her approach correct?
Show Answer
The 8-80 hour rule can be a useful local heuristic, but it is not a universal requirement. Stop decomposition when work packages can be reliably assigned, estimated, monitored, and controlled, while covering 100% of authorized scope.
Choose work-package detail appropriate to the project; hour limits alone do not establish a sound WBS.
Equipment costs INR 8,50,000. Straight-line over 9 years, salvage INR 51,000. Annual depreciation?
Show Answer
(8,50,000 - 51,000) / 9 = INR 88,778 per year.
Depreciation = (cost - salvage) / useful life
INR 4,04,000 needed in 2 years at 15% discount. Present value?
Show Answer
PV = 4,04,000 / (1.15)^2 = INR 3,05,482.
PV = FV / (1+r)^n
INR 2,71,000 needed in 5 years at 15% discount. Present value?
Show Answer
PV = 2,71,000 / (1.15)^5 = INR 1,34,735.
PV = FV / (1+r)^n
critical-thinking
A project scope statement covers 12 deliverables across 4 functional areas. Each deliverable averages 3 component-level requirements. How many total component requirements are in the scope statement?
Show Answer
12 deliverables x 3 requirements per deliverable = 36 component requirements
Component requirements are the detailed specifications within each deliverable
Governance
What three elements must every escalation path define?
Show Answer
(1) Escalation triggers — what conditions require escalation, (2) Escalation route — who to escalate to and in what order, (3) Escalation timeline — maximum time before escalation is required.
Triggers, route, and timeline
critical-thinking
What is continuous improvement (Kaizen) in project quality management?
Show Answer
The ongoing effort to incrementally improve processes, products, and services throughout the project by identifying waste, reducing variation, and incorporating lessons learned from each iteration or phase
Kaizen means small, continuous improvements rather than periodic overhauls
Risk Management
A risk register has 60 risks but only 5 have assigned owners. What does this indicate?
Show Answer
A governance failure — unowned risks will not be monitored or managed. The PM should immediately assign owners to all risks, document the rationale, and ensure owners understand their responsibilities.
Every risk needs an owner
critical-thinking
Kavitha is defining scope for a school management software project. The school principal wants grade reports, attendance tracking, fee management, and a library system. Kavitha knows the budget only covers the first three modules. What should Kavitha do?
Show Answer
Document the three funded modules as in-scope, clearly state the library module as out-of-scope in the scope statement, and note it as a potential Phase 2 addition
Explicitly document what is out of scope to prevent future demands
critical-thinking
Meera is managing a rural electrification project across 150 villages in Maharashtra. Her strategy must account for monsoon delays, supply chain disruptions, and varying community readiness. What should Meera include in her project strategy?
Show Answer
A risk response strategy with contingency buffers, a phased rollout approach by region, stakeholder engagement plans per village cluster, and a communication strategy for community leaders
Strategy must address the known challenges proactively — risk, phasing, and engagement
critical-thinking
A product owner uses a weighted shortest job first (WSJF) calculation: 3 features have the following scores (User-Business Value + Time Criticality + Risk Reduction) / Job Size: Feature A = (8+5+3)/5 = 3.2, Feature B = (10+4+2)/8 = 2.0, Feature C = (6+7+4)/3 = 5.67. Which feature should be done first?
Show Answer
Feature C with WSJF = 5.67 (highest ratio of value to effort)
WSJF maximizes value delivery rate by doing high-value, small-effort items first
Sprint Planning produces?
Show Answer
Sprint Planning produces the Sprint Backlog: the Sprint Goal (why), selected Product Backlog items (what), and the Developers' plan for delivering the Increment (how).
Sprint Backlog = why, what, and how.
Risk Management
What is risk monitoring and control?
Show Answer
The process of tracking identified risks, monitoring residual risks, identifying new risks, executing risk responses, and evaluating their effectiveness throughout the project lifecycle.
Track, monitor, identify new, execute responses, evaluate
Investment: INR 4,77,000. Returns: INR 9,25,380. ROI?
Show Answer
(9,25,380 - 4,77,000) / 4,77,000 x 100 = 94%.
ROI = (gain - cost) / cost x 100
A system failure risk has a transfer response. What does this involve?
Show Answer
Insurance, warranties, or contractual penalties that shift financial consequences to a third party.
Transfer shifts financial impact, not the event
Risk Management
A PM joins a project mid-way and finds no risk management plan exists. What should they do?
Show Answer
Assess immediate risk exposure while developing or tailoring a risk management plan with the team and relevant stakeholders. Obtain any approval required by the project's governance, and establish consistent identification, analysis, ownership, response, and review practices.
Establish the approach while addressing immediate exposure
critical-thinking
What is a schedule baseline and why is it important?
Show Answer
The approved version of the project schedule, used as the basis for comparing actual performance; it provides a benchmark against which schedule variances are measured and changes are controlled
Without a baseline, you cannot measure whether the project is ahead or behind
Issue Management
What factors should the PM consider when selecting an issue intervention?
Show Answer
Impact severity, urgency/time constraints, available resources, root cause (symptom vs. root), stakeholder expectations, cost-benefit of intervention options, and whether the intervention addresses root cause or just symptoms.
Impact, urgency, resources, root cause, stakeholders, cost
Team member wants to try an unproven approach. What should the PM do?
Show Answer
Allow in a time-boxed spike if the risk is manageable.
Spike equals safe experimentation
In ADKAR, what is Knowledge?
Show Answer
How to change -- skills and behaviors needed.
How to change
critical-thinking
A project's objective is 'improve employee productivity.' The PM proposes measuring it as 'reduce average task completion time by 25% within 6 months of go-live.' Is this a good benefits measurement?
Show Answer
Yes, because it is specific (25% reduction), measurable (task completion time), time-bound (6 months), and directly tied to the stated objective — it can be tracked before and after go-live
Good benefit metrics are SMART: Specific, Measurable, Achievable, Relevant, Time-bound
PV = INR 80,000, EV = INR 82,000. SPI?
Show Answer
SPI = 82,000 / 80,000 = 1.025 (approximately 1.03 with conventional half-up rounding). More budgeted work is complete than planned.
SPI = EV / PV. < 1 means behind.
Change Management
A project uses an emergency change procedure that allows the PM to approve changes under ₹2 lakhs without CCB review. An emergency change worth ₹1.8 lakhs is approved. What must the PM do AFTER implementation?
Show Answer
Record the emergency authorization and implementation, update affected controlled records, verify the result, and report to the CCB or other authority as required by the emergency change procedure. Retrospective review or ratification is required only when that procedure specifies it.
Follow the emergency procedure's reporting and review requirements
Issue Management
A risk response plan was to 'pre-qualify backup suppliers.' The risk materialized — the primary supplier failed. The backup supplier was not actually pre-qualified (paper only). Has the risk response failed, and what now?
Show Answer
Verify what prequalification and availability checks were actually completed. If the agreed response was not executed, record the supplier failure as an issue, activate authorized contingencies or urgent sourcing, and investigate the response gap. Prequalification does not by definition require an executed supply contract.
Verify the planned qualification work and available response
critical-thinking
Vendor Q's contract specifies delivery of 10,000 user records migrated with 99% accuracy. The project objective is to enable the customer service team to access migrated data. These are not the same. What should the PM do?
Show Answer
Align the contract deliverable with the project objective: define acceptance criteria that verify the data is accessible, usable, and meets the customer service team's operational requirements, not just a count
Contracts must be written for outcomes, not just outputs
Types of baselines?
Show Answer
Scope, Schedule, Cost (Performance Measurement Baseline).
Three primary baselines
What is a dependency?
Show Answer
A logical relationship between two activities where one must precede, follow, or overlap another.
Relationship between activities
INR 3,00,000 needed in 7 years at 8% discount. Present value?
Show Answer
PV = 3,00,000 / (1.08)^7 = INR 1,75,047.
PV = FV / (1+r)^n
critical-thinking
What is the purpose of negotiation in procurement management?
Show Answer
To reach a mutually acceptable agreement on terms, conditions, price, delivery, and other contract elements that satisfy both the buyer's project needs and the seller's business objectives
Negotiation creates value for both parties — it is not just about price
High power, low interest stakeholders?
Show Answer
Keep satisfied. They have influence but limited concern.
Key players with limited interest
Issue Management
How should issues be prioritized?
Show Answer
By impact severity (schedule, cost, scope, quality consequences), urgency (time sensitivity), and stakeholder visibility. High-impact, urgent, and highly visible issues should be escalated and resolved first. The issue log should display priority levels clearly.
Impact + Urgency + Visibility = Priority
Risk Management
A PM performs qualitative risk analysis on 40 identified risks. What output should this produce?
Show Answer
A prioritized risk register with probability-impact ratings (often visualized as a probability-impact matrix), risk scores, and risk categories. High-probability high-impact risks should be at the top, ready for detailed response planning.
Prioritized risk register
Investment: INR 1,10,000. Annual benefit: INR 73,000. Simple payback period?
Show Answer
1,10,000 / 73,000 = 1.5 years.
Simple payback = investment / annual benefit
critical-thinking
During activity execution, Suresh discovers that a server component his activity depends on will not be delivered on time. The supplier confirmed a 10-day delay. What should Suresh do FIRST?
Show Answer
Assess the impact on the project schedule using the network diagram, then escalate to the PM for a change request if the delay affects the critical path
Impact assessment comes before action — you need to know how bad it is before deciding what to do
Dependent stakeholders have?
Show Answer
Legitimacy + Urgency but no Power. Need advocacy.
Need representation
A contingency response is triggered when supplier progress reaches at least 80%. Current progress is 75%. Has that trigger fired?
Show Answer
No. The stated threshold has not been reached. Continue monitoring and assess whether emerging information requires an authorized revised response; do not claim that this trigger has fired.
Apply the agreed trigger condition
INR 1,95,000 invested at 12% for 6 years. Future value?
Show Answer
FV = 1,95,000 x (1.12)^6 = INR 3,84,895.
FV = PV x (1+r)^n
Risk Management
What should a risk status report include?
Show Answer
Current risk register summary (total risks, high-priority risks, new risks), risk exposure trends, effectiveness of risk responses, contingency reserve status, emerging risks, and any risks that have materialized into issues.
Risk summary, trends, response effectiveness, new risks
Norming phase characteristics?
Show Answer
Cohesion develops, roles clarified, group norms established.
Team starts working together effectively
critical-thinking
What is the purpose of analyzing financial requirements during project planning?
Show Answer
To identify the total funding needed across the project lifecycle, including upfront capital, operating expenditures, contingency reserves, and management reserves, ensuring the project is financially viable
Financial analysis prevents starting a project that cannot be funded to completion
Change Management
A developer implements an approved change by modifying code that was supposed to remain untouched per the change scope. The change 'works' but introduces side effects. What went wrong?
Show Answer
Poor implementation control — the developer exceeded the approved scope. The PM should have communicated the precise scope boundaries, provided updated work packages, and verified the change was implemented only within approved parameters.
Scope boundaries must be enforced during implementation
critical-thinking
In the PMP framework, what is the primary purpose of conducting a needs assessment during the development of the project management plan?
Show Answer
To understand stakeholder requirements, constraints, and assumptions before selecting an approach for delivering the project
Think about what comes before choosing an approach — you need to understand what stakeholders actually need
PERT: optimistic=5, most likely=17, pessimistic=29. Expected duration?
Show Answer
(5 + 4x17 + 29) / 6 = 17.00 days.
PERT = (O + 4M + P) / 6
Risk Management
A risk was mitigated by adding redundancy to a critical server. After 6 months, the server has not failed. Has the mitigation been effective?
Show Answer
Not yet conclusively — the absence of the risk event doesn't prove the mitigation worked. It could be low probability. Effectiveness should be assessed through technical verification (redundancy tested), statistical confidence, and comparison against the original probability estimate.
Absence of event ≠ proof of effectiveness
Compliance
A compliance audit finds that the project's access control system does not meet the required standard. 30% of user accounts have excessive privileges. What action should the PM take FIRST?
Show Answer
Initiate a corrective action to remediate the excessive privileges immediately, then conduct a root cause analysis to understand why the access controls were improperly configured, and implement preventive actions.
Fix first, then prevent recurrence
Motivation theories: Herzberg?
Show Answer
Hygiene factors prevent dissatisfaction. Motivators create satisfaction.
Two factors
INR 1,92,000 needed in 8 years at 12% discount. Present value?
Show Answer
PV = 1,92,000 / (1.12)^8 = INR 77,546.
PV = FV / (1+r)^n
Governance
What level of detail is usually least useful in a steering committee's governance status report?
Show Answer
Detailed task-level updates for individual team members — governance reporting should focus on milestones, risks, issues, budget, and strategic alignment, not operational task lists.
Governance reports are strategic, not operational
Directing (situational leadership)?
Show Answer
High directive, low supportive. For new, enthusiastic followers.
Tell them what, how, when
critical-thinking
Using PERT analysis: a task has an optimistic estimate of 8 days, most likely of 12 days, and pessimistic of 26 days. What is the PERT expected duration?
Show Answer
(8 + 4(12) + 26) / 6 = 82 / 6 = 13.67 days
PERT formula: (O + 4M + P) / 6
critical-thinking
Meera is delivering a hospital management system. She proposes 3 increments: (1) patient registration, (2) appointment scheduling, (3) billing and reporting. Each increment is independently usable. What value does this approach deliver?
Show Answer
The hospital can start using patient registration immediately (Increment 1) while later increments are developed, delivering business value early rather than waiting for the complete system
Each usable increment delivers value independently of the others
PV = INR 25,000, EV = INR 39,000. SPI?
Show Answer
SPI = 39,000 / 25,000 = 1.56. Ahead of schedule.
SPI = EV / PV. < 1 means behind.
What is a team charter?
Show Answer
A document defining team purpose, goals, norms, and working agreements.
Team agreement
What is fitness for use?
Show Answer
The degree to which a product meets user needs and intended use.
Fitness for use = customer perspective
Governance
How does a project governance structure differ from a project management plan?
Show Answer
Governance structure defines WHO makes decisions and provides oversight (roles, committees, authority levels), while the project management plan defines WHAT will be done, HOW it will be done, and WHEN (schedule, processes, baselines).
Governance = people and authority; Plan = work and processes
critical-thinking
Priya is a PM leading a hospital digitization project in Bengaluru. During a needs assessment, she discovers three separate departments have conflicting requirements for the EMR system. What should Priya do FIRST?
Show Answer
Facilitate a prioritization workshop with all stakeholders to align on a unified set of requirements before proceeding
Clarify conflicting requirements and facilitate alignment before committing to a unified solution.
Investment: INR 4,58,000. Annual benefit: INR 84,000. Simple payback period?
Show Answer
4,58,000 / 84,000 = 5.5 years.
Simple payback = investment / annual benefit
critical-thinking
What is the purpose of reviewing the project management plan before baseline establishment?
Show Answer
To verify that all subsidiary plans (scope, schedule, cost, quality, resource, communication, risk, procurement, stakeholder) are aligned, complete, and consistent with the project charter and enterprise environmental factors
Resolve inconsistencies before seeking approval for the integrated plan and applicable baselines.
Investment: INR 1,59,000. Annual benefit: INR 42,000. Simple payback period?
Show Answer
1,59,000 / 42,000 = 3.8 years.
Simple payback = investment / annual benefit
critical-thinking
A project has a 20-month baseline with work planned uniformly over time. At month 8, 30% of the total budgeted work has been earned. What are its current progress gap and a simple completion forecast if this progress rate continues?
Show Answer
Planned progress is 8/20 = 40%; earned progress is 30%, a gap of 10 percentage points. Under the uniform plan, earned schedule is 0.30 x 20 = 6 months, so the current time gap is 2 months. Continuing the current rate gives a total duration of 8/0.30 = 26.67 months, about 6.67 months later than baseline.
A current delay and the forecast delay at completion are different measures.
What is a change request?
Show Answer
A formal proposal to modify any aspect of the project.
Formal modification proposal
Equipment costs INR 8,38,000. Straight-line over 9 years, salvage INR 75,420. Annual depreciation?
Show Answer
(8,38,000 - 75,420) / 9 = INR 84,731 per year.
Depreciation = (cost - salvage) / useful life
Risk Management
A risk's probability increases from low to high after a regulatory change. What should the PM do?
Show Answer
Update the risk register with the new probability assessment, reassess the impact, recalculate the risk score, escalate if the risk now exceeds the threshold for the current response strategy, and inform the risk owner to activate or escalate the response plan.
Update, reassess, escalate if needed
What are the five predictive project management process groups?
Show Answer
Initiating, Planning, Executing, Monitoring and Controlling, Closing.
Process groups can recur within phases; they are not the project lifecycle phases.
Backlog = 196 points, velocity = 40 points/sprint. How many sprints?
Show Answer
196 / 40 = 4.9. Round up to 5 sprints.
Sprints = ceiling(backlog / velocity)
Compliance
A PM identifies GDPR compliance threats involving a legacy database, third-party analytics, offshore development, and manual data entry. How should the highest-priority threat be determined?
Show Answer
Confirm applicability and assess each threat's likelihood, consequences for individuals and the project, data flows, existing safeguards, and response urgency with privacy specialists. The involvement of a third party alone does not determine the ranking.
Analyze actual exposure and safeguards before ranking
Risk Management
A PM identifies a 40% probability of a regulatory approval being delayed by 6 months and proposes active acceptance using schedule contingency. How should this response be made actionable?
Show Answer
Assess the potential schedule impact and risk tolerance, size the contingency using a suitable analysis, and agree ownership, monitoring, and any trigger-based actions. Monetary EMV and a fallback plan may help in some contexts, but are not prerequisites for every acceptance response.
Active acceptance uses agreed contingency and monitoring
Governance
Priya is leading a ₹12 crore digital transformation project for a manufacturing firm in Pune. The steering committee meets monthly but key decisions take 3 weeks because no one knows who has budget approval authority. What governance element is missing?
Show Answer
A clearly defined authority matrix (RACI or similar) that specifies decision rights, budget approval thresholds, and escalation paths for each governance body.
What governance document prevents decision delays?
critical-thinking
A project manager uses PERT for a critical design task. Optimistic = 5 days, Most Likely = 10 days, Pessimistic = 23 days. What is the standard deviation of this estimate?
Show Answer
(Pessimistic - Optimistic) / 6 = (23 - 5) / 6 = 3 days
PERT standard deviation formula: (P - O) / 6
critical-thinking
Rajesh's project needs both custom software development (core capability) and office cleaning services (support). How should Rajesh approach procurement differently for each?
Show Answer
Custom software: detailed statement of work, competitive bidding with technical evaluation, and a fixed-price or T&M contract. Office cleaning: simple service agreement, price-based evaluation, and a fixed-price contract with clear SLAs
Different procurement needs require different approaches — complexity drives process sophistication
Issue Management
What is the difference between a project risk and a project issue?
Show Answer
A risk is a potential future event that may or may not occur. An issue is a current condition or event that is already affecting the project and requires immediate action. Risk = 'what might happen;' Issue = 'what is happening now.'
Risk = potential; Issue = actual
What is Juran's approach to quality?
Show Answer
Fitness for use: quality that meets customer needs. Focus on the user perspective.
Juran = fitness for use
critical-thinking
Before awarding a contract, the PM realizes the vendor's understanding of the project objective differs from the buying organization's. The vendor thinks the goal is speed, while the buyer values accuracy. What should the PM do?
Show Answer
Pause the procurement process, conduct a scope alignment meeting with the vendor, and ensure the contract explicitly prioritizes accuracy as the primary objective
Misalignment on objectives before contract award is cheaper to fix than after
critical-thinking
What is resource leveling in project management?
Show Answer
A resource optimization technique that adjusts activity start and finish dates based on resource constraints and availability to resolve resource over-allocations without changing the project scope
Leveling spreads work to match resource availability, potentially extending the project duration
INR 1,27,000 invested at 12% for 2 years. Future value?
Show Answer
FV = 1,27,000 x (1.12)^2 = INR 1,59,309.
FV = PV x (1+r)^n
critical-thinking
What is the quality management plan and what does it include?
Show Answer
A component of the project management plan that describes how the project's quality policies will be implemented, including quality standards, quality control and assurance activities, continuous improvement processes, and roles and responsibilities for quality
The quality management plan is the 'how' of achieving quality objectives
critical-thinking
What is incremental delivery in the context of value-based project delivery?
Show Answer
Delivering the project in sequential increments, where each increment delivers a usable subset of the total product, service, or result, enabling early value realization and feedback incorporation
Incremental delivery means the customer gets value before the project is 100% complete
Governance
A vendor offers complimentary premium seats at a cricket match worth ₹80,000 to the project manager overseeing a ₹5 crore vendor evaluation. The PM accepts. What governance ethics breach has occurred?
Show Answer
Conflict of interest and potential bribery — accepting significant gifts from a vendor under evaluation compromises objectivity and violates most organizational ethics policies. The PM should decline and report the offer.
PM discovers the project has been going in the wrong direction. What should they do?
Show Answer
Immediately communicate, assess damage, propose corrections.
Earlier correction costs less
What is Deming's approach?
Show Answer
System of profound knowledge: appreciation for a system, knowledge of variation, theory of knowledge, and psychology.
Deming = systems thinking
Risk Management
What is the difference between a security risk and an IT risk?
Show Answer
IT risks concern information technology and can include system failures, integration, obsolescence, and suppliers. Security risks concern protection of information, people, systems, and physical assets. They overlap in cybersecurity, but physical security threats need not be IT risks.
Cybersecurity overlaps IT; physical security may not
Issue Management
A PM has 15 open issues. 2 are blocking the critical path, 5 are affecting non-critical work, and 8 are minor complaints. How should the PM prioritize resolution?
Show Answer
Focus resources on the 2 critical-path blockers immediately, schedule the 5 non-critical issues into current sprints, and address the 8 minor issues during normal work or batch them for a future sprint.
Critical blockers first, then the rest by impact
Risk Management
What is a probability-impact matrix and how is it used?
Show Answer
A grid that plots probability (likelihood) against impact (consequence) to categorize risks. High probability + high impact risks go in the top-right (red) zone and need active management. Low probability + low impact risks may be accepted.
P-I Matrix = risk prioritization grid
INR 1,80,000 needed in 3 years at 12% discount. Present value?
Show Answer
PV = 1,80,000 / (1.12)^3 = INR 1,28,120.
PV = FV / (1+r)^n
PM notices a team member is consistently negative. What should they do?
Show Answer
Speak privately to understand the concerns and their effect on the team, listen to relevant feedback, and agree constructive expectations and support. Address continuing harmful behavior through the appropriate performance process.
Understand the concern and coach constructively before taking personnel action.
Regulatory requirement changes mid-project. What should the PM do?
Show Answer
Confirm applicability and effective dates with qualified specialists, assess impacts on requirements, scope, schedule, cost, and risk, and route needed changes through the defined approval process. Update affected controlled records and verify compliance with the applicable obligation.
Confirm applicability and timing, then authorize the required response
High power, high interest stakeholders?
Show Answer
Manage closely. These are key players who can make or break the project.
Key players
Change Management
A change is approved that modifies the risk response strategy for an existing risk. What documentation must be updated?
Show Answer
The risk register (response strategy, risk owner, and residual risk), risk report, and any risk response plans. If the change creates new risks, the identification process must be repeated and the risk register updated accordingly.
Risk register first, then risk report
critical-thinking
Meera's team estimates a data migration activity at 10 days. When it actually took 18 days because the source database had corrupted records, Meera realized the estimate was based on clean-data assumptions. What lesson does this teach about estimating?
Show Answer
Estimates must account for uncertainty and risk — assumptions should be documented, and contingency reserves should be added for known risk factors
Estimates based on ideal assumptions without risk buffers will be wrong when risks materialize
critical-thinking
An infrastructure project in Gujarat requires INR 85 crore total. The project team estimates a 20% probability of cost overrun due to monsoon delays. What should the PM include in the financial analysis?
Show Answer
Estimate the financial impact of monsoon delays as well as their probability, then quantify contingency using an appropriate risk analysis and organizational risk tolerance. A 20% probability alone does not justify a 20% budget contingency or an INR 102 crore estimate.
Expected monetary exposure requires probability and impact; contingency is not probability multiplied by the total budget.
critical-thinking
Why is it important to reassess value throughout a project?
Show Answer
Because business conditions, stakeholder needs, market dynamics, and technology landscapes change during a project's lifecycle, making original value assumptions potentially invalid
Value reassessment ensures the project continues to deliver relevant value in a changing environment
Issue Management
At what point does a risk become an issue?
Show Answer
When an uncertain event or condition actually exists, record and manage the actual problem as an issue. Activate any applicable authorized risk responses and update the linked risk information; remaining uncertainties still require risk management.
Actual occurrence creates an issue; retain applicable planned responses
critical-thinking
What is the purpose of defining project scope?
Show Answer
To describe the work that must be performed to deliver a product, service, or result with specified features and functions, and to explicitly state what is out of scope to prevent scope creep
Scope definition creates a shared understanding of what IS and IS NOT included
Compliance
A social media platform project fails to comply with India's IT Rules for content moderation. The platform is banned for 3 months. What is the primary consequence?
Show Answer
Operational — the platform cannot generate revenue during the ban. Secondary consequences include reputational damage, user attrition, and potential legal penalties. This illustrates how compliance consequences cascade across categories.
One compliance failure, multiple consequence types
Risk Management
What is the difference between a risk response and a contingency plan?
Show Answer
A risk response includes the chosen strategy and agreed actions. A contingency plan is a predefined response activated under specified conditions or triggers and can implement active acceptance. A fallback plan is a further response used when the selected response is ineffective or inadequate.
Contingency is a planned response; fallback addresses response failure
critical-thinking
The sponsor defines value as 'maximizing shareholder returns.' The project team defines value as 'delivering quality on time.' The customer defines value as 'getting all requested features.' What should the PM do?
Show Answer
Facilitate a value alignment workshop to establish a shared value framework with agreed metrics that balance all perspectives, then prioritize deliverables accordingly
Conflicting value definitions must be resolved before value-based delivery can proceed
Compliance
A compliance audit identifies 25 requirements. After classification: 8 critical, 12 important, 5 desirable. The project has 3 months and limited budget. How should the PM prioritize?
Show Answer
Confirm which requirements are mandatory, prioritize their implementation by consequence, urgency, and dependencies, and escalate any resource shortfall. Voluntary aspirations may be deferred through the authorized process; required compliance cannot be waived merely because an item is classified as important or desirable.
Prioritize the work while preserving mandatory obligations
critical-thinking
What is a schedule variance and how is it calculated?
Show Answer
The difference between earned value (EV) and planned value (PV) at a given point in time: SV = EV - PV. A positive SV means ahead of schedule; negative means behind
SV tells you whether you are ahead or behind at the measurement point
Servant leader removes impediments?
Show Answer
Yes. The primary role is to enable the team to do their best work.
Removing obstacles is the core
Risk Management
A PM identifies 85 risks for a ₹15 crore infrastructure project. The risk register is complete but no analysis has been done. What is the next step?
Show Answer
Qualitative risk analysis — assess probability and impact to prioritize the risks. Having 85 unprioritized risks is not actionable. The PM should use a probability-impact matrix to rank them for response planning.
Identify → Analyze → Plan responses
Stakeholder keeps bypassing the PM to talk to the team. What should the PM do?
Show Answer
Clarify whether requests or decisions are bypassing an agreed control process. Support useful direct collaboration while agreeing clear channels for commitments, scope changes, and decisions that require authorization.
Encourage collaboration and clarify decision authority.
Team suggests a non-value-added feature. What should the PM do?
Show Answer
Challenge the request. Does it deliver customer value? Reject or defer.
Say no to waste
Issue Management
A team member consistently misses deadlines, causing cascading delays. A quick intervention is to reassign their tasks. What is a more thorough intervention?
Show Answer
Root cause analysis — understand why the team member is missing deadlines (skill gap, personal issues, unclear expectations, too much workload). Reassigning tasks treats the symptom; addressing the root cause prevents recurrence and may help retain the team member.
Root cause > symptom treatment
Motivation theories: Vroom?
Show Answer
Expectancy theory: Motivation = Expectancy x Instrumentality x Valence.
Three factors multiply
Compliance
A payment processing project must comply with PCI DSS. The PM classifies PCI DSS requirements as 'critical.' What is the consequence of this classification?
Show Answer
All PCI DSS compliance activities receive highest priority in scheduling, resourcing, and testing. Any design decision that could affect PCI DSS compliance triggers mandatory review. Non-compliance could mean losing the ability to process card payments entirely.
PCI DSS noncompliance can jeopardize payment acceptance
critical-thinking
What is an integrated project management plan and what does it integrate?
Show Answer
A comprehensive document that consolidates all subsidiary plans (scope, schedule, cost, quality, resource, communication, risk, procurement, stakeholder) and baselines into a coherent framework for executing, monitoring, and closing the project
It is the 'master plan' that brings all knowledge areas together
Active listening involves?
Show Answer
Fully concentrating, understanding, responding, and remembering what is being said.
More than hearing
critical-thinking
A team member reports that a 4-day activity is progressing well and will finish 1 day early. The PM celebrates but then learns the activity was completed by skipping a mandatory quality check. What should the PM do?
Show Answer
Address the quality gap immediately — early completion that sacrifices quality may create rework and actually delay the project. Stop the celebration and assess the true impact
Schedule performance without quality compliance is false progress
A quality baseline is?
Show Answer
The specific quality measures set for the project to serve as a benchmark.
Baseline = measurement target
What is fast tracking?
Show Answer
Performing activities in parallel that were planned sequentially.
Risk for speed
critical-thinking
Vikram creates a WBS dictionary entry for the 'User Interface Module' work package. What minimum information should this dictionary entry include?
Show Answer
A description of the work, the acceptance criteria, the responsible party, the required resources, the estimated schedule, the cost estimate, and any technical references or constraints
A WBS dictionary provides the detailed information needed to execute each work package
Investment: INR 2,12,000. Annual benefit: INR 97,000 for 8 years at 12%. NPV?
Show Answer
Total PV of benefits: INR 4,81,861. NPV = 4,81,861 - 2,12,000 = INR 2,69,861. Project is financially viable.
NPV = PV of benefits - PV of costs
Team wants to pair program but customer sees it as wasteful. What should the PM do?
Show Answer
Explain the potential benefits for quality, learning, and knowledge continuity, then agree a proportionate trial or evidence review to assess the actual impact in this team.
Evaluate the technique's benefits with evidence.
PM has conflicting directives from two managers. What should they do?
Show Answer
Clarify authority per the project charter and RACI.
Clarity on authority
Two departments want conflicting features. What should the PM do?
Show Answer
Facilitate discussion, reference the business case, escalate if needed.
Align competing requirements with agreed objectives and decision authority.
In ADKAR, what is Ability?
Show Answer
Implementing the change in practice.
Doing the change
Issue Management
A sprint board shows 4 blockers for 3 consecutive days. The PM asks if they are still blocking. The team says 'yes, same ones.' What should the PM do?
Show Answer
Confirm each blocker's impact, owner, resolution progress, and next action. Work with the relevant team or process owner and escalate when the defined impact, urgency, or authority threshold is reached. Coordinate any needed Sprint scope adaptation with the appropriate roles.
Escalate using impact, urgency, and authority thresholds
Issue Management
An issue causes a 2-week delay to a non-critical-path activity. The PM evaluates impact and finds float absorbs the delay. What should the PM document?
Show Answer
Document the issue, assessed delay, float consumed, owner, current status, and remaining exposure. If the baseline can still be achieved, no baseline change is automatically needed. Close the issue only after its resolution has been verified.
No baseline impact does not mean the issue is resolved
critical-thinking
Priya needs a cloud hosting service for her project. She can either use the organization's existing cloud vendor (convenient but expensive) or go through a competitive RFP process (time-consuming but potentially cheaper). What should Priya consider?
Show Answer
Evaluate actual supplier-selection lead times, validated price and service comparisons, urgency, switching and integration costs, and organizational procurement policy. Use current evidence for this procurement rather than assuming a standard saving or duration.
Source-selection decisions balance evidenced cost, time, capability, and policy.
PM discovers success criteria are ambiguous. What should they do?
Show Answer
Work with stakeholders to clarify and document SMART criteria.
Ambiguous criteria create disputes
Risk Management
What is a risk audit and when should it be conducted?
Show Answer
A structured review of risk management effectiveness — examining whether risk responses are being implemented, whether the risk register is current, and whether the risk management process is working. Risk audits should be conducted at major milestones and when significant risk events occur.
Risk audit = check if risk management is working
Competing (TKI) =?
Show Answer
High assertiveness, low cooperativeness. Force your viewpoint.
I win, you lose
Compliance
How often should compliance be measured during a project?
Show Answer
Set review and measurement frequency according to applicable obligations, risk, control behavior, project milestones, and governance needs. Combine suitable continuous monitoring with periodic verification, and document the agreed cadence and trigger points.
Tailor frequency to obligations and exposure
critical-thinking
Activity X is on the critical path with a duration of 7 days. It has 0 days of total float. Activity Y is not on the critical path with a duration of 5 days. The project currently has 2 days of total float on Activity Y. If Activity Y slips by 3 days, what happens to the project duration?
Show Answer
The 3-day slip exceeds Activity Y's 2 days of total float by 1 day. With unchanged dependencies and no recovery action, project completion is delayed by 1 day. The original total project duration was not supplied.
Delay beyond total float affects project completion.
critical-thinking
What is scope decomposition in project management?
Show Answer
The process of subdividing project deliverables and work into smaller, more manageable components until the work packages are identified, enabling more accurate estimating, scheduling, and execution
Decomposition breaks scope down to a level where work can be planned and controlled
Finish-to-Finish (FF)?
Show Answer
Successor cannot finish until predecessor finishes.
Parallel finish
Path A(9d)->B(17d)->C(9d) = 35 days. Path A(9d)->D(12d) = 21 days. Total float on second path?
Show Answer
14 days of total float.
Total float = critical path - alternative path
PERT: optimistic=1, most likely=11, pessimistic=28. Expected duration?
Show Answer
(1 + 4x11 + 28) / 6 = 12.17 days.
PERT = (O + 4M + P) / 6
INR 1,36,000 needed in 7 years at 10% discount. Present value?
Show Answer
PV = 1,36,000 / (1.10)^7 = INR 69,790.
PV = FV / (1+r)^n
Economic feasibility means?
Show Answer
The project's benefits justify its costs.
Does it make financial sense?
PERT: optimistic=2, most likely=8, pessimistic=30. Expected duration?
Show Answer
(2 + 4x8 + 30) / 6 = 10.67 days.
PERT = (O + 4M + P) / 6
Governance
In a matrix organization, the project governance structure must clearly define which authority resides with the functional manager versus the project manager. What is this principle called?
Show Answer
Authority allocation — it defines who makes what decisions, who approves expenditures, and who resolves conflicts to prevent power vacuums that delay project decisions.
Consider the distribution of decision-making power
Risk Management
A risk response plan involves 'mitigating supplier delay risk by pre-qualifying two backup suppliers.' When should the PM execute this response?
Show Answer
Complete supplier prequalification before it is needed, according to the approved response plan and latest feasible decision date. Confirm capability and availability, and establish any agreements the plan requires. A supplier contract is not automatically required merely to complete prequalification.
Execute mitigation before the response option expires
Finish-to-Start (FS)?
Show Answer
Successor cannot start until predecessor finishes. Most common.
Sequential
critical-thinking
At the project's month 6 review (of a 12-month baseline), PV = INR 2.4 crore, EV = INR 2.1 crore, and AC = INR 2.5 crore. Calculate SV, SPI, CV, and CPI.
Show Answer
SV = EV - PV = 2.1 - 2.4 = -0.3 (INR 30 lakhs behind). SPI = EV/PV = 2.1/2.4 = 0.875 (87.5% efficient). CV = EV - AC = 2.1 - 2.5 = -0.4 (INR 40 lakhs over). CPI = EV/AC = 2.1/2.5 = 0.84 (84% cost efficient)
All four EVM indices calculated from the same three values — SV/SPI show schedule; CV/CPI show cost
Issue Management
A PM discovers a team member has been hiding a technical issue for 3 weeks because they hoped to solve it quietly. The issue has now become critical. What governance principle was violated?
Show Answer
Transparency and issue visibility — issues must be raised promptly. The PM should address this with the team member constructively (not punitively), review the reporting culture, and ensure the issue escalation process is clear and psychologically safe.
Hidden issues grow; Safe escalation prevents hiding
critical-thinking
A project's critical path totals 40 days. An independent noncritical path totals 37 days, giving it 3 days of total float. An activity on that path slips by 5 days. With unchanged dependencies and calendars, what is the new project duration?
Show Answer
The noncritical path increases from 37 to 42 days. It consumes its 3 days of float and adds 2 days to the original 40-day duration. The project now takes 42 days.
Recalculate the longest path after the delay.
critical-thinking
The business wants all 20 features delivered in the first release. The development team says they can only build 8 features in the available time. What should the PM facilitate?
Show Answer
A value-based prioritization workshop using WSJF or MoSCoW to select the 8 highest-value features for Release 1, with the remaining 12 scheduled for subsequent releases
Value-based delivery means delivering the RIGHT features, not ALL features
critical-thinking
What is the difference between Fixed-Price Incentive Fee (FPIF) and Fixed-Price with Economic Price Adjustment (FPEPA)?
Show Answer
FPIF shares cost savings/overruns between buyer and seller based on a formula with target cost, target fee, and ceiling price. FPEPA adjusts the fixed price based on external economic conditions (e.g., inflation, material cost indices)
FPIF = performance-based; FPEPA = market-condition-based
A risk of data breach has an avoid response. What does this involve?
Show Answer
Eliminating the risk condition: remove the vulnerable data, use anonymized data, or not store sensitive data.
Avoidance removes the risk condition
Compliance
How should a PM assess the consequences of noncompliance for a fintech project in India?
Show Answer
Identify the specific applicable obligations and assess legal, financial, operational, safety, and reputational consequences with qualified specialists. Severity depends on the actual activity, breach, authority, and response deadline; no compliance area is automatically highest for every fintech project.
Assess the specific obligation and actual consequences
Risk Management
Risk A has 60% probability and ₹30 lakhs impact. Risk B has 20% probability and ₹1 crore impact. Which has higher EMV?
Show Answer
Risk A: 0.60 × 30 = ₹18 lakhs EMV. Risk B: 0.20 × 100 = ₹20 lakhs EMV. Risk B has higher EMV despite lower probability, due to its much larger impact. EMV helps identify high-consequence low-probability risks.
EMV reveals the true risk exposure
What is a SWOT analysis?
Show Answer
Strengths, Weaknesses, Opportunities, Threats. Internal and external factors.
Four-factor analysis
Change Management
A PM uses a change control process where all changes must be submitted in writing with impact analysis. A senior executive verbally requests a change during a steering committee meeting. What should the PM do?
Show Answer
Politely explain the change control process, note the request formally in the meeting minutes, and initiate the formal change request process. The PM should not implement verbal changes regardless of who requests them.
Process applies to everyone, including executives
critical-thinking
What are the four types of activity dependencies in project scheduling?
Show Answer
Finish-to-Start (FS): successor cannot start until predecessor finishes; Start-to-Start (SS): successor cannot start until predecessor starts; Finish-to-Finish (FF): successor cannot finish until predecessor finishes; Start-to-Finish (SF): successor cannot finish until predecessor starts (rarely used)
These four dependency types define the logical relationships between activities
How does an operations-improvement project differ from ongoing operations?
Show Answer
An operations-improvement project is a temporary initiative that creates a defined change or capability for operations. Operations are the continuing activities that sustain products or services.
A temporary change initiative is a project; continuing service delivery is operations.
critical-thinking
Rajesh's team has been producing software defects at a rate of 8 per 1000 lines of code. His quality management plan targets 3 defects per 1000 lines. Should Rajesh focus on QA or QC first?
Show Answer
Use QC to assess and correct affected deliverables, while QA or manage-quality activities investigate and improve the processes causing defects. The urgency and release context determine sequencing; high defect rates require both product control and prevention.
Prevent recurrence and address existing nonconformance.
Internal failure costs include?
Show Answer
Rework, scrap, re-inspection, failure analysis.
Fixing defects before delivery
Investment: INR 4,92,000. Annual benefit: INR 56,000. Simple payback period?
Show Answer
4,92,000 / 56,000 = 8.8 years.
Simple payback = investment / annual benefit
critical-thinking
The WBS for a school construction project shows 'Building Shell' decomposed into 'Foundation,' 'Structure,' and 'Roofing.' 'Roofing' is further broken into 'Material Procurement,' 'Installation,' and 'Inspection.' At what level is 'Inspection' in this hierarchy?
Show Answer
Work package level (Level 3 or Level 4 depending on counting method) — it is a discrete unit of work that can be assigned, estimated, and scheduled independently
A work package is the lowest level of the WBS where work can be uniquely assigned and tracked
Supporting (situational leadership)?
Show Answer
Low directive, high supportive. For competent but variable motivation.
Facilitate, encourage
Equipment costs INR 7,66,000. Straight-line over 2 years, salvage INR 68,940. Annual depreciation?
Show Answer
(7,66,000 - 68,940) / 2 = INR 3,48,530 per year.
Depreciation = (cost - salvage) / useful life
PM is replaced mid-project. What should they do?
Show Answer
Capture critical project knowledge, current status, plans, decisions, risks, issues, and pending commitments, then arrange a structured handoff to the incoming PM.
Transfer the knowledge and responsibilities needed for continuity.
critical-thinking
During financial reporting planning, Vikram realizes his project has multiple funding sources: INR 1.5 crore from the parent company, INR 50 lakh from a government grant, and INR 30 lakh from a partner organization. What must Vikram account for in his reporting plan?
Show Answer
Each funding source may have different reporting requirements, audit trails, and compliance standards — his reporting plan must accommodate all requirements separately
Multiple funding sources = multiple reporting obligations
Virtual team best practices?
Show Answer
Regular structured contact, shared tools, clear norms, intentional relationship building.
Deliberate design
Issue Management
What is an issue log and what information must it contain?
Show Answer
A project document that records and tracks all project issues. Required information: issue ID, description, date raised, raised by, impact assessment (scope, schedule, cost, quality), priority, assigned owner, target resolution date, status, and resolution date.
Issue log = the project's issue tracker
critical-thinking
Six months after project completion, the PM is asked to verify benefit realization. The original metric was 'reduce processing time by 30%.' Current data shows 18% reduction. The sponsor asks if the project failed. What should the PM explain?
Show Answer
The target benefit has not been fully achieved: the reduction is 18% against 30%. Assess why, whether the realized value is worth the effort and expense, and what the agreed success criteria require. On-time, on-budget scope delivery alone does not establish overall project success.
Evaluate success using stakeholder value and agreed outcomes as well as delivery performance.
critical-thinking
Vendor R is INR 5 lakh over budget. The PM's negotiation BATNA (Best Alternative to Negotiated Agreement) is to go to Vendor S, who quoted INR 3 lakh above budget with slightly lower quality. What should the PM's walk-away point be?
Show Answer
Compare Vendor R's proposed terms with Vendor S's credible alternative using total value, quality, cost, risk, and any hard budget constraint. Determine an authorized reservation point from that comparison; the prices alone do not establish an INR 2 lakh walk-away limit.
BATNA informs the reservation point through total value, not an arbitrary price discount.
critical-thinking
Three vendors submitted proposals for a project. Vendor A scores highest technically (92/100) but is 20% more expensive. Vendor B scores 75/100 technically but is cheapest. Vendor C scores 88/100 and is 8% above average cost. What is the best selection approach?
Show Answer
Apply the predefined weighted evaluation criteria, including the method for converting cost into a comparable score and any mandatory qualification thresholds. The given technical scores and relative prices are insufficient to establish a winner.
A weighted result requires scores for every weighted criterion.
critical-thinking
What does optimizing resource availability mean in project management?
Show Answer
Ensuring that required resources are available when needed through effective acquisition, development, and deployment strategies, including training, cross-training, resource pooling, and flexible scheduling
Optimization means making the best use of available resources within constraints
Compliance
When should compliance requirements be identified in the project lifecycle?
Show Answer
At initiation through a compliance assessment, refined during planning, validated at each stage gate, and continuously monitored throughout execution. Early identification prevents costly redesigns.
Identify early, monitor always
Change Management
A PM receives a change approved by the CCB but the CCB minutes do not document the rationale. What should the PM do?
Show Answer
Confirm that approval is valid and request the decision authority to record the rationale in the controlled change records. Follow any documentation prerequisites in the change-control plan, then implement and verify the authorized change without inventing additional approval conditions.
Preserve valid authorization and the decision trail
A stakeholder wants to see detailed tasks. What should the PM do?
Show Answer
Share appropriate detail and refer to the communications plan.
Match detail to need
Transactional leadership emphasizes?
Show Answer
Exchange-based: rewards for performance, penalties for non-performance.
Structure and rewards
What is a stakeholder register?
Show Answer
A living record of identified stakeholders and their relevant attributes, such as roles, interests, expectations, influence, and classification. Detailed engagement strategies and actions are documented in the stakeholder engagement plan.
Foundation of stakeholder management
Governance
How should delivery metrics and product outcome metrics relate to overall project success?
Show Answer
Assess delivery performance together with outcomes, stakeholder value, and benefits relative to effort and expense. On-time, on-budget delivery alone does not establish overall project success if the result fails to create the intended value.
Project success includes value and outcomes
Compliance
What is the difference between a compliance threat and a project risk?
Show Answer
A compliance threat is a condition or uncertainty that could prevent the project meeting applicable obligations. Project risk is broader: uncertainty can have positive or negative effects on any objective. Compliance threats are part of the project's risk exposure.
Project risk includes threats and opportunities
PV = INR 33,000, EV = INR 32,000. SPI?
Show Answer
SPI = 32,000 / 33,000 = 0.97. Behind schedule.
SPI = EV / PV. < 1 means behind.
Change Management
What are the six steps of a typical change control process?
Show Answer
(1) Submit change request, (2) Log and categorize, (3) Impact assessment (scope, schedule, cost, quality, risk), (4) Review and approve/reject by CCB, (5) Implement approved change, (6) Update project documents and verify.
Request → Log → Assess → Approve → Implement → Verify
Governance
What is the relationship between governance ethics and stakeholder trust?
Show Answer
Governance ethics directly build or erode stakeholder trust — transparent, fair, and accountable governance creates confidence in the project's legitimacy and outcomes, while unethical governance undermines it irreparably.
Ethical governance = trusted governance
Downward communication is?
Show Answer
Communication from sponsor/management to team. Needs clarity and context.
From the chain above
critical-thinking
Vendor X submitted a proposal INR 3 lakh below budget but claims they can complete the work in 4 months. The PM knows from industry knowledge that similar work typically takes 5-6 months. What should the PM do?
Show Answer
Request a detailed work breakdown and timeline from Vendor X, verify their approach against industry benchmarks, and scrutinize the proposal for scope gaps or hidden assumptions
Unusually low bids often hide scope gaps, assumptions, or later change requests
Compliance
What is a control self-assessment (CSA) in the context of project compliance?
Show Answer
A structured process where project team members evaluate their own compliance controls, identifying gaps and weaknesses before an external audit. It builds compliance awareness, creates early warning signals, and distributes accountability across the team.
CSA = team self-audit
Who is responsible for quality?
Show Answer
Everyone. The PM ensures processes are followed, but all team members produce quality work.
Quality is everyone's responsibility
For a conventional three-sigma control chart of normally distributed individual measurements, where are the control limits set?
Show Answer
At the process mean plus and minus three standard deviations; under the stated normal-distribution assumption, about 99.73% of individual measurements lie within that interval.
Control-limit calculations depend on chart type and statistical assumptions.
Investment: INR 1,98,000. Annual benefit: INR 41,000 for 6 years at 12%. NPV?
Show Answer
Total PV of benefits: INR 1,68,568. NPV = 1,68,568 - 1,98,000 = INR -29,432. Project is not viable at this rate.
NPV = PV of benefits - PV of costs
Adjourning phase characteristics?
Show Answer
Disbanding, recognition, documentation, transition.
Team completes and disbands