PMP Risk Management Questions 2026: Concepts, Responses and 8 Practice Questions

Gulab Chand Tejwani
PMP · PL-300 · Microsoft Certified Trainer
· 11 min read

In the 2026 PMP exam, risk management sits in the Business Environment domain as Task 5, "Plan and manage risk". The exam expects you to tell a risk (uncertain, in the future) from an issue (already happening), to pick the right response strategy for threats and opportunities, to know who owns a risk, and to use reserves and expected monetary value correctly. This post covers those concepts and then tests them with eight practice questions.
I'm Gulab Chand Tejwani, PMP and Microsoft Certified Trainer. Risk used to be a Process topic, and plenty of study material still files it there. The move to Business Environment matters less for what you study than for how questions are framed: expect risk to show up next to governance, compliance and external change, not just inside a schedule.
What is risk management on the PMP exam?
Project risk is any uncertain event or condition that, if it happens, has a positive or negative effect on at least one project objective. Negative risks are threats. Positive risks are opportunities. Risk management is the ongoing work of identifying them, analysing them, planning responses, carrying out those responses and monitoring the results.
"Ongoing" is the word the exam leans on. Risk identification isn't a planning-phase ceremony. On agile projects it happens every iteration, in planning, stand-ups and retrospectives. On predictive projects it's revisited at every major review. A question where the project manager "already completed the risk register during planning" and therefore ignores a new risk is setting a trap.

What is the difference between a risk and an issue?
- Risk: might happen. Lives in the risk register. You plan a response.
- Issue: has happened. Lives in the issue log. You act on it.
When a risk you identified actually happens, it becomes an issue, and you carry out the response you planned. When something happens that you never identified, you use a workaround: an unplanned response to an unplanned event. Then you add it to the register so the project learns from it.
What are the risk response strategies?
| Response | Threat example | Opportunity example |
|---|---|---|
| Escalate | A supplier risk that affects the whole programme goes to the programme manager | A pricing opportunity beyond your authority goes to the sponsor |
| Avoid / Exploit | Change the design to remove an untested component | Assign your best developer to make sure an early-release bonus is earned |
| Transfer / Share | Buy insurance or a fixed-price contract | Partner with a firm to win a larger contract together |
| Mitigate / Enhance | Add extra testing to reduce defect probability | Add resources to raise the chance of finishing early |
| Accept | Note the risk and set aside contingency (active) or do nothing (passive) | Take the benefit if it happens, without chasing it |
Two details students miss:
- Escalate is for risks outside the project's scope or the project manager's authority. Escalated risks are owned at programme, portfolio or organization level and aren't monitored by the project team afterwards.
- Transfer moves ownership of the impact, usually for a price (insurance premium, contractor's margin). It doesn't remove the risk.
How do reserves work?
- Contingency reserve is for identified risks, the "known unknowns". It's part of the cost baseline, and the project manager usually controls its use within the risk plan.
- Management reserve is for unidentified risks, the "unknown unknowns". It sits outside the cost baseline but inside the project budget, and using it normally needs management approval through change control.
How do you calculate expected monetary value?
Expected monetary value (EMV) = probability × impact. Threats have negative impact and opportunities positive. Add EMVs across risks to size a contingency reserve.
Example: a 30% chance of a ₹50,000 penalty (EMV −₹15,000) and a 20% chance of a ₹20,000 early-delivery bonus (EMV +₹4,000). Net EMV = −₹11,000.

Practice questions
A risk you identified during planning, that a cloud provider might raise prices mid-contract, has just happened. The risk register lists a response: move non-critical workloads to an approved alternative provider. What should you do?
- ALog the price rise in the issue log and wait for the sponsor's instructions
- BHold a team workshop to brainstorm new responses
- CImplement the planned response and update the risk register and issue log
- DAsk the provider to reverse the increase
Show answer and explanation
Correct answer: C
The risk happened and a response is already approved. Carry it out, then record what happened and watch for secondary risks from the move. A and B ignore the plan, and D might be worth a try but isn't the planned response.
Your team uses a third-party payment library that may stop being maintained next year. Which response is an example of risk avoidance?
- ABuy a support contract from a company that maintains forks of the library
- BChange the design to use the payment provider's officially supported SDK instead
- CAdd extra automated tests around the payment module
- DRecord the risk and review it each quarter
Show answer and explanation
Correct answer: B
Avoidance removes the risk by changing the plan, so the library is no longer part of the solution. A is transfer, C is mitigation, and D is acceptance.
During a sprint review, a stakeholder mentions that a new tax rule may change invoice formats across the whole company next year. It affects several projects, not just yours. What should you do?
- AAdd it to your risk register and plan a mitigation
- BIgnore it, since it's outside your project's scope
- CAsk the team to start building the new format now
- DEscalate it to the programme or portfolio level that can own it
Show answer and explanation
Correct answer: D
A risk that spans several projects and sits beyond your authority is a candidate for escalation. Note that you still communicate it: ignoring it (B) is wrong. Once escalated, it's owned at the higher level.
Your project's risk analysis shows three identified threats with EMVs of −₹40,000, −₹25,000 and −₹15,000, and one opportunity with an EMV of +₹10,000. What contingency reserve does this analysis support?
- A₹70,000
- B₹80,000
- C₹90,000
- D₹10,000
Show answer and explanation
Correct answer: A
Net EMV = −40,000 − 25,000 − 15,000 + 10,000 = −70,000, so a ₹70,000 contingency reserve. B ignores the opportunity.
An unidentified risk occurs: a fire at a subcontractor's site destroys components. The project needs ₹3 lakh to replace them. Which reserve should normally fund this?
- AContingency reserve, controlled by the project manager
- BThe team's sprint buffer
- CManagement reserve, with management approval
- DNo reserve; cut scope instead
Show answer and explanation
Correct answer: C
An unidentified risk is an unknown unknown, which management reserve exists for. Using it typically needs approval and a change to the cost baseline through change control.
You've just implemented a response to a vendor-delay risk by switching to a second vendor. The second vendor is new to your industry and may misunderstand requirements. What is this new risk called?
- AResidual risk
- BSecondary risk
- CTrigger
- DWorkaround
Show answer and explanation
Correct answer: B
A secondary risk arises directly from implementing a risk response. Residual risk is what's left of the original risk after the response. A trigger is a warning sign that a risk is about to happen.
Your agile team has an opportunity: if the release is ready two weeks early, the client will feature the product at its annual conference. What is the best way to enhance this opportunity?
- AAccept it and see what happens
- BShare it with a partner company
- CTell the client the date is guaranteed
- DWork with the product owner to prioritise the features needed for the conference and remove impediments
Show answer and explanation
Correct answer: D
Enhancing increases the probability or impact of an opportunity. Focusing the backlog on what the conference needs and clearing blockers raises the chance of an early, useful release. C makes a promise the team can't guarantee.
Three months into the project, a team member notices that a key subcontractor has missed two weekly status reports, which the risk register lists as a warning sign of financial trouble. What should you do?
- ATreat it as a risk trigger: inform the risk owner and prepare to carry out the planned response
- BWait until the subcontractor actually misses a delivery
- CTerminate the subcontract immediately
- DAdd a new risk for missed status reports
Show answer and explanation
Correct answer: A
The register already names this as a trigger. The risk owner should be told so the planned response can start in time. B wastes the warning, C is drastic without analysis, and D duplicates a risk you've already identified.
What do the right answers have in common?
Look back over the eight. The project manager in each one uses the risk process that already exists (the register, the planned response, the owner, the reserves) instead of improvising. They escalate only what really sits outside their authority, and they keep risk work continuous rather than treating planning as the end of it. That's the mindset the exam rewards.
How should you prepare for risk questions?
Learn the ten response strategies with one example each from your own work, and practise EMV until it's automatic. Then do risk questions mixed with the rest of the Business Environment domain, because that's how they'll arrive. The Business Environment practice questions cover governance, compliance and change alongside risk, and the PMP case study post shows how a risk sits next to an issue in one longer scenario.
When you're ready to test it under time pressure, our PMP mock exams use the 2026 format: 180 questions in 240 minutes, with a domain breakdown so you can see how you're doing in Business Environment specifically. The first full mock is free (no card needed).
TechNet Consultancy is independent and not affiliated with PMI.
If you are just starting out, read how to prepare for the PMP exam in 2026 first.
FAQ
Which domain is risk management in on the 2026 PMP exam?
Business Environment. "Plan and manage risk" is Task 5 of that domain in PMI's July 2026 outline. In the 2021 outline it was in the Process domain.
What are the five risk response strategies for threats?
Escalate, avoid, transfer, mitigate and accept. For opportunities they are escalate, exploit, share, enhance and accept.
What is the difference between contingency reserve and management reserve?
Contingency reserve covers identified risks and is part of the cost baseline. Management reserve covers unidentified risks, sits outside the baseline, and usually needs management approval to use.
What is the difference between a risk and an issue?
A risk is an uncertain future event. An issue is something that has already happened. When an identified risk occurs, it becomes an issue and you carry out the planned response.
What is a secondary risk?
A risk created by carrying out a risk response, for example a new vendor's inexperience after you switch vendors to avoid a delay.